Pembangunan Embung Rawa Malang Ditargetkan Rampung Akhir Mei
....
photo Rezki Apriliya Iskandar - Beritajakarta.id

Rawa Malang Embung Construction Has Touched 40 Percent

The Semper Timur Urban Village, Cilincing, North Jakarta continues to speed up the Rawa Malang Embung (artificial lake) construction on Jalan Cakung Cilincing Drainase Kampung Sawah, RT 10/11.

To conduct it, we use heavy equipment such as one unit of Amphibious XM 22 and one unit of excavator

Cilincing Sub-district Water Resources (SDA) Executing Unit Head, Tjahyono Budi Setiawan said it has been constructed since November 4, 2020 and was targeted to be complete by the end of the upcoming May.

"Currently, the progress is still 40 percent due to constraints on the construction of the Cibitung - Cilincing Toll Road piles. Nearly a quarter of the construction area was part of the work of the Cibitung - Cilincing Toll Road by PT Waskita Beton Precast Tbk (WSBP). Yet we continue to coordinate with the Waskita regarding the solution," he expressed, Thursday (3/25).

Embung Development Work on Jalan Letjen Suprapto Accelerated

He went on to say that the work was executed on the 4.5-hectare width land belongs to the SDA agency. The embung would have six meters depth wit DAM around 1.5 meters height.

"To conduct it, we use heavy equipment such as one unit of Amphibious XM 22 and one unit of excavator. Eight personnel have also been alerted at the location," he continued.

He explained it was aimed at tackling inundation in the surrounding area, especially during the rainy season.

"After it is done, we hope the inundation problem can be resolved," he hoped.

Not only that, it also aimed to accommodate water in order to increase groundwater sources in the surrounding area. It was also designed to be one of the ecotourism spots in North Jakarta area.

"Later, locals can do exercise and other activities. Not far from the location, there is also Malang Rawa Urban Forest. So, the facilities will be more complete," he stated.

Linked News
Popular News indeks
  1. 1,262 Personnel Ready to Support Bhayangkara Anniversary Cleanliness

    access_time30-06-2025 remove_red_eye573 personAldi Geri Lumban Tobing
  2. UK Royal Marine Band Enlivens Jakarta Anniversary

    access_time27-06-2025 remove_red_eye561 personDessy Suciati
  3. 19,675 People Visit Ragunan Zoo on Islamic New Year

    access_time27-06-2025 remove_red_eye471 personTiyo Surya Sakti
  4. Video Mapping and Dancing Fountain Entertain Monas Visitors

    access_time27-06-2025 remove_red_eye395 personBudhi Firmansyah Surapati
  5. Transjakarta Wins Award for Best GCG Company

    access_time27-06-2025 remove_red_eye392 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik