146,47 M3 Lumpur Berhasil Dikeruk di PHB Sulaiman

Dredging Work is Conducted at Sulaiman Connecting Channel in Kebon Jeruk

Kebon Jeruk Sub-district Water Resources (SDA) Unit, West Jakarta, dredged Sulaiman connecting (phb) channel on Jl. Yusuf. From this dredging work, personnel collected 146.47 cubic meters of mud.

Our target is to finish the dredging work in July 2021

Kebon Jeruk Sub-district SDA Unit Head, Suprapto conveyed, Sulaiman phb channel has total length of 744 meters, while current work has reached 320 meters. This work has been carried out since May 3, 2021.

"Our target is to finish the dredging work in July 2021," he stated, Monday (6/28).

Kali Sunter River Normalization Enters Land Acquisition Stage

According to him, mud thickness in Sulaiman phb channel reached around 100 centimeters to 1 meter. TIn this dredging work, 36 Kebon Jeruk Sub-district SDA Unit personnel and 10 PPSU personnel were deployed to clean up channel manually using hoe, bucket, crowbar, and cart.

"Dredging will optimize channel's capacity thus it can hold more water, especially when heavy rain falls. Besides, it is hoped to minimize inundation in the surrounding area," he explained.

Linked News
Popular News indeks
  1. BI and Jakarta Government Deepen Investment, Creative Economy Collaboration

    access_time09-11-2026 remove_red_eye537 personAldi Geri Lumban Tobing
  2. Governor Approves Removal of Seven Unauthorized Houses on Dispora Land

    access_time13-11-2026 remove_red_eye522 personFakhrizal Fakhri
  3. Transjakarta Offers Free Rides for Jakarta Vertical Run 2026 Participants

    access_time14-11-2026 remove_red_eye516 personAldi Geri Lumban Tobing
  4. Pramono Outlines Measures to Address Five Issues in Kramat Jati

    access_time13-11-2026 remove_red_eye515 personFakhrizal Fakhri
  5. Jakarta Esports 2026 Draws Enthusiastic Crowds at M Bloc Space

    access_time13-11-2026 remove_red_eye497 personTiyo Surya Sakti