Some 11 personnel of the Kemayoran Sub-district Water Resources (SDA) Executing Unit, Central Jakarta have started dredging the water channel located on Jalan Serdang Baru IX, Serdang Urban Village.

It has been going on since the end of September and is targeted to be complete in a month

Sub-district SDA Executing Unit Head, Supriyadi expressed, it was realized to follow up on the residents' aspirations in the Musrenbang.

The channel itself was dredged manually up to 502 meters length with 70 centimeters width, 1.1 meters height and one meter depth.

Cilangkap Reservoir Dredging Progress Reaches 35 Percent

"It has been going on since the end of September and is targeted to be complete in a month," he expressed, Wednesday (10/20).

He hoped that it could accommodate water in large quantities in the rainy season in a bid to anticipate flooding.

"So far it has touched 30 percent," he said.

Linked News
Popular News indeks
  1. Pramono Inaugurates GMAHK Taman Harapan Jakarta

    access_time25-10-2026 remove_red_eye534 personDessy Suciati
  2. JRF, Ye Concert Inject Rp 625 Billion into Jakarta's Economy

    access_time26-10-2026 remove_red_eye509 personDessy Suciati
  3. Transjakarta Adjusts Routes Amid Demonstrations

    access_time28-10-2026 remove_red_eye483 personAldi Geri Lumban Tobing
  4. Tourism Industry Workforce Capacity Continues to Be Improved

    access_time30-10-2026 remove_red_eye420 personAldi Geri Lumban Tobing
  5. Munjirin Encourages Government and Residents to Implement Waste Sorting

    access_time30-10-2026 remove_red_eye419 personNurito