Pengerjaan Saluran Air di Pulau Untung Jawa Ditargetkan Selesai Akhir Depan
....
photo Anita Karyati - Beritajakarta.id

Saturday, Channel Construction on Untung Jawa Island Completed

The water channel which is being built in RT 02/02, Untung Jawa Island Urban Village, South Seribu Islands is targeted to be completed on Saturday (4/23). It has been ongoing since Monday (4/18).

Thus far, the progress has reached more than 50 percent

Seribu Islands Water Resouces (SDA) Sub-agency Head Hendri said the construction of the 140-meter-long channel used four- and six-inch paralon pipes that were attached 50 centimeters deep. Its channel was equipped with four control tubs measuring 80x60 centimeters.

"Thus far, the progress has reached more than 50 percent," he said, Thursday (4/21).

Clogged Channel on Jalan H. Nisin Pekayon Cleaned

He added the work involved around 13 workers using simple tools like hoes, crowbars, buckets, plywood, and sacks.

"Hope it can minimize flooding," he hoped.

Linked News
Popular News indeks
  1. 250 High School Students in N. Jakarta Learn to Create Digital Content

    access_time01-11-2024 remove_red_eye794 personBudhi Firmansyah Surapati
  2. W. Jakarta SDA Constructs Channel on Jalan Nurul Muslimin I Kembangan

    access_time04-11-2024 remove_red_eye774 personTP Moan Simanjuntak
  3. 18 School Principals Participate in Public Agency E-Monev Presentation

    access_time02-11-2024 remove_red_eye474 personFolmer
  4. Tanah Tinggi Residents Participate in Computer Operator Training

    access_time02-11-2024 remove_red_eye373 personBudhi Firmansyah Surapati
  5. Semongol River Dredging Intensified

    access_time06-11-2024 remove_red_eye331 personTP Moan Simanjuntak