Saturday, Channel Construction on Untung Jawa Island Completed
access_time April 21 2022 03:56 PM remove_red_eye 486
Reported by Anita Karyati | Translated by Nugroho Adibrata
Reported by Anita Karyati | Translated by Nugroho Adibrata
The water channel which is being built in RT 02/02, Untung Jawa Island Urban Village, South Seribu Islands is targeted to be completed on Saturday (4/23). It has been ongoing since Monday (4/18).
Thus far, the progress has reached more than 50 percent
Seribu Islands Water Resouces (SDA) Sub-agency Head Hendri said the construction of the 140-meter-long channel used four- and six-inch paralon pipes that were attached 50 centimeters deep. Its channel was equipped with four control tubs measuring 80x60 centimeters.
"Thus far, the progress has reached more than 50 percent," he said, Thursday (4/21).
Clogged Channel on Jalan H. Nisin Pekayon CleanedHe added the work involved around 13 workers using simple tools like hoes, crowbars, buckets, plywood, and sacks.
"Hope it can minimize flooding," he hoped.