Pembangunan Saluran Air di Bambu Apus Capai 95 Persen
....
photo Istimewa - Beritajakarta.id

This Week, Channel Construction in Bambu Apus Completed

The water chanmel located on Jalan H. Karim RT 03/03 Bambu Apus Urban Village, Cipayung, East Jakarta that is conducted from October 5, targeted to be finished this week.

The work progress has touched 95 percent

Cipayung Sub-district Water Resources (SDA) Executing Unit Head, Dian Kartika said the channel construction along 26 meters long with a high of 1.2 meters and 80 centimeters wide was built to connect existing water channels that have been broken.

"The work progress has touched 95 percent," she expressed, Wednesday (10/25).

SDA Sub-agency Builds Channels in Cilangkap

She explained it was done manually. Basically, the base was made of bodeman so it would be sturdy.

"10 personnel of task force are involved to smoothen the work," she explained.

She added it was done to follow up on residents' proposal in the Musrenbang 2023.

Linked News
Popular News indeks
  1. 250 High School Students in N. Jakarta Learn to Create Digital Content

    access_time01-11-2024 remove_red_eye795 personBudhi Firmansyah Surapati
  2. W. Jakarta SDA Constructs Channel on Jalan Nurul Muslimin I Kembangan

    access_time04-11-2024 remove_red_eye780 personTP Moan Simanjuntak
  3. 18 School Principals Participate in Public Agency E-Monev Presentation

    access_time02-11-2024 remove_red_eye479 personFolmer
  4. Tanah Tinggi Residents Participate in Computer Operator Training

    access_time02-11-2024 remove_red_eye377 personBudhi Firmansyah Surapati
  5. 104 Wild Cats in Kebayoran Lama Sterilized

    access_time07-11-2024 remove_red_eye347 personTiyo Surya Sakti