Channel Normalization on Jalan Batu to Complete May
Reported by Budhi Firmansyah Surapati | Translated by Rizky Mawardi
The normalization of water channel on Jalan Batu, RT 08/01, Gambir Urban Village, Central Jakarta, is targeted to complete in May.
We deploy 18 personnel
Gambir Sub-district's Water Resource Implementer Unit Head, Mohamad Imawan, said channel in residential areas which is 20 centimeters wide with a height of around 20 centimeters is improved to 40 centimeters wide and 60 centimeters high.
Ancol Barat Connecting Water Channel Dredging to Complete this Week"We also replace channel's material along 72 meters with u-ditch concrete," he said, Tuesday (4/30).
According to him, the normalization responds residents' request during Musrenbang 2024.
"The work has been started since yesterday. We deploy 18 personnel," he added.
According to him, the work has reached 20 percent and is targeted to complete in mid May.
One of residents of RW 01 Gambir Mulyana, appreciated the channel dredging. Previously, he stated, the area was often inundated since the channel was too narrow.
"It is hoped the dredging will finish on time and prevent inundation," he hoped.