 Anwar Tinjau Pembangunan Saluran Air di Jl Jambore
.
photo Nurito - Beritajakarta.id

Anwar: Flooding on Jalan Jamboree can Be Resolved

East Jakarta Mayor, Muhammad Anwar and his staff, inspected the construction of a water channel using the jacking system method on Jalan Jamboree Cibubur, Ciracas, Tuesday (8/20).

The work progress has touched 15 percent," he stated

According to him, the construction of the water channel using the jacking system method was to overcome the puddles that often occur at that location every time there is heavy rain. Traffic was experiencing disruption and drivers were forced to look for alternative routes in nearby locations.

"This is to overcome puddles as high as 50 to 80 centimeters at that location every time it rains," he expressed.

Anwar Hands Over Aid to SDN Pondok Bambu 01

He was optimistic that the construction of a channel using a jacking system can overcome inundation, as the volume and discharge of water that will enter the Rawa Dongkal Reservoir area has been measured.

"It is targeted to be completed by the end of this November," he explained.

East Jakarta Water Resources Sub-agency's Development Section Head, Tengku Saugi Zikri added the work has been ongoing since early August.

According to him, the jacking system was implemented to minimize the impact of construction because it does not take up much space for excavation. So, traffic could still pass, even though there is infrastructure work.

He mentioned the jacking pipe that will be installed for this channel is 370 meters long, starting from the corner near the steel shop to SMPN 147.

The materials used U-Ditch 150x150x120 centimeters, box culvert measuring 120x110 x100 centimeters, U-Ditch measuring 80x80x120 centimeters.

"Hope it can finish on the target," he stressed.

Of the total length of 370 meters of pipe that must be installed, 220 meters are ready for drilling and installation. The pipe was planted to six meters deep.

As planned, on August 24, excavation construction would be executed on Jalan SMPN 147. So far, there are no technical problems because the cable utilities can still be resolved.

"East Jakarta Mayor, Muhammad Anwar and his staff, inspected the construction of a water channel using the jacking system method on Jalan Jamboree Cibubur, Ciracas, Tuesday (8/20).

According to him, the construction of the water channel using the jacking system method was to overcome the puddles that often occur at that location every time there is heavy rain. Traffic was experiencing disruption and drivers were forced to look for alternative routes in nearby locations.

"This is to overcome puddles as high as 50 to 80 centimeters at that location every time it rains," he expressed.

He was optimistic that the construction of a channel using a jacking system can overcome inundation, as the volume and discharge of water that will enter the Rawa Dongkal Reservoir area has been measured.

"It is targeted to be completed by the end of this November," he explained.

East Jakarta Water Resources Sub-agency's Development Section Head, Tengku Saugi Zikri added the work has been ongoing since early August.

According to him, the jacking system was implemented to minimize the impact of construction because it does not take up much space for excavation. So, traffic could still pass, even though there is infrastructure work.

He mentioned the jacking pipe that will be installed for this channel is 370 meters long, starting from the corner near the steel shop to SMPN 147.

The materials used U-Ditch 150x150x120 centimeters, box culvert measuring 120x110 x100 centimeters, U-Ditch measuring 80x80x120 centimeters.

 

"Hope it can finish on the target," he stressed.

Of the total length of 370 meters of pipe that must be installed, 220 meters are ready for drilling and installation. The pipe was planted to six meters deep.

As planned, on August 24, excavation construction would be executed on Jalan SMPN 147. So far, there are no technical problems because the cable utilities can still be resolved.

"The work progress has touched 15 percent," he stated," he stated.

Linked News
Popular News indeks
  1. Jakarta Vice Governor Rano Wishes a Happy Eid al-Fitr 1446 Hijri

    access_time31-03-2025 remove_red_eye593 personFolmer
  2. Monas Prepares to Greet Visitors This Eid Holiday

    access_time30-03-2025 remove_red_eye585 personDessy Suciati
  3. Foul Smell Around JGC Clarified Not Coming from Rorotan RDF

    access_time28-03-2025 remove_red_eye431 personAldi Geri Lumban Tobing
  4. Residents Hope Another Free Homecoming Program Held Next Year

    access_time27-03-2025 remove_red_eye316 personDessy Suciati
  5. Odd-Even Policy in Jakarta Put on Hold for Eid Break

    access_time28-03-2025 remove_red_eye288 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik