SDA Jakpus Normalisasi Saluran Air di Jalan Percetakan Negara VB

Channel Normalization on Jl Percetakan Negara VB to Complete June

Channel normalization on Jalan Percetakan Negara VB, RT 06 and 07 of RW 03, Rawasari Urban Village, Cempaka Putih, Central Jakarta is targeted to complete this mid June.

Now the progress has reached 90 percent

Cempaka Putih District Water Resource Implementer Unit Head, Sahudi explained the 336 meters-long water channel is being normalized since February ago by using u-ditch concrete.

"Now the progress has reached 90 percent. It is targeted to complete this mid June," Sahudi said, Monday (6/2).

Arrangement of Jalan Bukit Duri Utara Raya Area Reaches 90 Percent

According to him, the normalization is run to accommodate resident aspiration.

"The channel was unable to flow water smoothly. It triggers inundation," he added.

Roland (48), one of local residents, appreciated the channel normalization. He hopes it will eliminate the inundation during the heavy rain.

"Hopefully it can be completed on time to avoid inundation during rainy season," he hoped.

Linked News
Popular News indeks
  1. 21 Parking Spots to Make Your Jakarta 499th Anniversary Experience Seamless

    access_time26-06-2026 remove_red_eye947 personAldi Geri Lumban Tobing
  2. Over 11 Kilometers of Overhead Utility Cables Removed in West Jakarta

    access_time26-06-2026 remove_red_eye900 personBudhi Firmansyah Surapati
  3. Celebrating Jakarta`s 499th Anniversary at HI, Please Use Public Transportation

    access_time26-06-2026 remove_red_eye763 personAldi Geri Lumban Tobing
  4. 190 Satpol PP Personnel Deployed to Secure Jakarta Anniversary Celebration

    access_time26-06-2026 remove_red_eye721 personFolmer
  5. Night at The Library Marks Jakarta's 499th Anniversary with Five-Century Message

    access_time27-06-2026 remove_red_eye710 personAnita Karyati