SDA Jakpus Normalisasi Saluran Air di Jalan Percetakan Negara VB

Channel Normalization on Jl Percetakan Negara VB to Complete June

Channel normalization on Jalan Percetakan Negara VB, RT 06 and 07 of RW 03, Rawasari Urban Village, Cempaka Putih, Central Jakarta is targeted to complete this mid June.

Now the progress has reached 90 percent

Cempaka Putih District Water Resource Implementer Unit Head, Sahudi explained the 336 meters-long water channel is being normalized since February ago by using u-ditch concrete.

"Now the progress has reached 90 percent. It is targeted to complete this mid June," Sahudi said, Monday (6/2).

Arrangement of Jalan Bukit Duri Utara Raya Area Reaches 90 Percent

According to him, the normalization is run to accommodate resident aspiration.

"The channel was unable to flow water smoothly. It triggers inundation," he added.

Roland (48), one of local residents, appreciated the channel normalization. He hopes it will eliminate the inundation during the heavy rain.

"Hopefully it can be completed on time to avoid inundation during rainy season," he hoped.

Linked News
Popular News indeks
  1. Jakarta to Hold Citywide Lights-Out Initiative

    access_time24-04-2026 remove_red_eye778 personAldi Geri Lumban Tobing
  2. Suckerfish Handling in South Jakarta is Run in Accordance with MUI Recommendations

    access_time21-04-2026 remove_red_eye661 personTiyo Surya Sakti
  3. Jakarta Residents Welcome Rp1 Public Transport Fare

    access_time24-04-2026 remove_red_eye569 personNurito
  4. Limiting Gadget Use in Schools Expected to Boost Interaction and Reading Habits

    access_time24-04-2026 remove_red_eye550 personFakhrizal Fakhri
  5. Rano Leads Parking Arrangement on Jalan R.A. Kartini, Lebak Bulus

    access_time24-04-2026 remove_red_eye547 personBudhi Firmansyah Surapati