Channel Normalization on Jalan Petamburan 3 to Complete End of July

The water channel normalization on Jalan Petamburan III RW 04, Petamburan, Tanah Abang, run by Central Jakarta Water Resources Sub-agency, is targeted to complete this month.

eliminate the inundation

Tanah Abang Water Resource Unit Head, Eli Menawan Sari said there are two points where the channel is normalized with a total length of 190 meters. The work has been running since May 19 by involving nine personnel.

Eli explained the first location is at Gang Paksi along 159 meters. This work has been completed in June.

Six Points along Ciliwung River Being Dredged from Mud

"Now we are normalizing channel on Jalan Petamburan 3 heading Jalan KS Tubun along 40 meters," he said, Friday (7/11).

He added that the normalization is run based on residents request at Musrenbang 2025.

 

Agung (40), local resident, appreciated the normalization run by the personnel.

"Hopefully the normalization will eliminate the inundation here," he hoped.

Linked News
Popular News indeks
  1. Jakarta to Hold Citywide Lights-Out Initiative

    access_time24-04-2026 remove_red_eye802 personAldi Geri Lumban Tobing
  2. Jakarta Residents Welcome Rp1 Public Transport Fare

    access_time24-04-2026 remove_red_eye618 personNurito
  3. Limiting Gadget Use in Schools Expected to Boost Interaction and Reading Habits

    access_time24-04-2026 remove_red_eye596 personFakhrizal Fakhri
  4. Rano Leads Parking Arrangement on Jalan R.A. Kartini, Lebak Bulus

    access_time24-04-2026 remove_red_eye573 personBudhi Firmansyah Surapati
  5. PT JIEP Targets Shenzhen Businesses with Investment Offers

    access_time24-04-2026 remove_red_eye566 personAldi Geri Lumban Tobing