Channel Normalization on Jalan Petamburan 3 to Complete End of July

The water channel normalization on Jalan Petamburan III RW 04, Petamburan, Tanah Abang, run by Central Jakarta Water Resources Sub-agency, is targeted to complete this month.

eliminate the inundation

Tanah Abang Water Resource Unit Head, Eli Menawan Sari said there are two points where the channel is normalized with a total length of 190 meters. The work has been running since May 19 by involving nine personnel.

Eli explained the first location is at Gang Paksi along 159 meters. This work has been completed in June.

Six Points along Ciliwung River Being Dredged from Mud

"Now we are normalizing channel on Jalan Petamburan 3 heading Jalan KS Tubun along 40 meters," he said, Friday (7/11).

He added that the normalization is run based on residents request at Musrenbang 2025.

 

Agung (40), local resident, appreciated the normalization run by the personnel.

"Hopefully the normalization will eliminate the inundation here," he hoped.

Linked News
Popular News indeks
  1. Jakarta Council Begins Deliberations on New Population and Housing Bylaws

    access_time21-08-2026 remove_red_eye1809 personFakhrizal Fakhri
  2. Jakarta Assesses Needs and Coordinates Aid for NTT Earthquake Victims

    access_time16-08-2026 remove_red_eye736 personAldi Geri Lumban Tobing
  3. Jakarta Prepares Aid for NTT Earthquake Victims

    access_time16-08-2026 remove_red_eye688 personDessy Suciati
  4. Pramono: Independence must Be Manifested Through Concrete Action

    access_time17-08-2026 remove_red_eye686 personDessy Suciati
  5. Pramono Commends Madurese Community for Their Vital Role in Building Jakarta

    access_time19-08-2026 remove_red_eye658 personDessy Suciati