Pengendara Diimbau Hindari Jalan DI Panjaitan Ruas Cawang-Kebon Nanas

Traffic Diverted at Jalan DI Panjaitan for Channel Construction

The East Jakarta Water Resources (SDA) Sub-agency is detouring traffic on Jalan DI Panjaitan, Cawang to Kebon Nanas, to allow for the construction of the water channel using Jacking method.

This work is divided into five phases

Seeing that, motorists are urged to avoid that road segment to prevent traffic congestion caused by the narrowing of the usable lane.

East Jakarta Transportation Sub-agency's Traffic Section Staff, Dedy said, preparations for construction are underway at several points on Jalan DI Panjaitan.

Normalization of Water Channel on Jalan Taman Sari Almost Done

"We have implemented traffic diversion to minimize congestion from in front of Wika Building to the U-turn at Cawang Baru," he expressed, Monday (8/11).

East Jakarta Development Section Head, Tengku Saugi Zikri explained, the channel construction has begun today.

"Work begins from the side of Cawang Underpass to the Kalimalang intersection. Physical excavation work is slated to start from August 30 to December 22, 2025," he explained.

He assessed, the first phase of the Jacking channel construction will begin in front of Park Hotel Cawang on August 11 and will end at the eighth stage in front of Brantas Abipraya 2 Building.

"This work is divided into five phases, and the work will be executed at night from 10 PM to 4 AM," he assessed.

Here are the stages of the water channel construction on Jalan DI Panjaitan:

1. Joint Pit 1 started from August 11 to October 19, 2025, in front of Park Hotel

2. Joint Pit 2 started from September 10 to October 16, 2025, in front of Patria Park

3. Joint Pit 3 started from August 14 to November 22, 2025, in front of Yodya Karya

4. Joint Pit 4 started from October to November 22, 2025, in front of Wika Tower

5. Joint Pit 5 started from September 12 to December 21, 2025, in front of Perumnas

6. Joint Pit 6 started from November 12 to December 21, 2025, in front of Perumnas

7. Joint Pit 7 started from August 21 to November 27, 2025, in front of Brantas 1

8. Joint Pit 8 started from August 30 to December 22, 2025, in front of Brantas 2

Linked News
Popular News indeks
  1. 21 Parking Spots to Make Your Jakarta 499th Anniversary Experience Seamless

    access_time26-06-2026 remove_red_eye938 personAldi Geri Lumban Tobing
  2. Over 11 Kilometers of Overhead Utility Cables Removed in West Jakarta

    access_time26-06-2026 remove_red_eye896 personBudhi Firmansyah Surapati
  3. Celebrating Jakarta`s 499th Anniversary at HI, Please Use Public Transportation

    access_time26-06-2026 remove_red_eye755 personAldi Geri Lumban Tobing
  4. 190 Satpol PP Personnel Deployed to Secure Jakarta Anniversary Celebration

    access_time26-06-2026 remove_red_eye719 personFolmer
  5. Night at The Library Marks Jakarta's 499th Anniversary with Five-Century Message

    access_time27-06-2026 remove_red_eye704 personAnita Karyati