Repair of Collapsed Retaining Wall in Batu Ampar Completed

The repair of collapsed water channel retaining wall on Jalan Batu Sadi I, RT 10/02, Batu Ampar Urban Village, Kramat Jati District, East Jakarta has been completed fully.

completed in seven days

Head of Kramat Jati Water Resources Unit, Muchlis explained the retaining wall, approximately 10 meters long and 1.2 meters high, collapsed due to heavy rain that poured down on the area last week.

Water Channel on Jalan Rawa Binong Being Improved

"We deployed seven Blue Taskforce personnel assisted by PPSU. The repair was run manually," he said, Thursday (11/6).

He added that the work was hampered by the water channel being blocked by concrete cast by residents. Therefore, it had to be dismantled first using a breaker.

"Thankfully the work has been completed in seven days," he added.

Meanwhile, LMK RW 02, Batu Ampar Urban Village, Siti Zuriyah appreciated the quick response of the unit to repair the retaining wall.

"We directly reported the incident when the retaining wall collapsed. As the work has been completed, the residents feel safe and comfortable," she admitted.

Linked News
Popular News indeks
  1. Fire at Pondok Bambu Allegedly Triggered by Electrical Short

    access_time19-05-2026 remove_red_eye1384 personNurito
  2. Governor Pramono Named Vice Chair of C40 Cities Steering Committee

    access_time18-05-2026 remove_red_eye1018 personAldi Geri Lumban Tobing
  3. Inundation on DI Panjaitan Road Recede

    access_time20-05-2026 remove_red_eye845 personNurito
  4. Dharma Jaya Ready for Thousands of Eid al-Adha Sacrifices

    access_time20-05-2026 remove_red_eye655 personAldi Geri Lumban Tobing
  5. Rasuna Said Car-Free Day to Return in June 2026

    access_time16-05-2026 remove_red_eye637 personAldi Geri Lumban Tobing