Channel Normalization on Jalan Karet Pasar Baru Barat 1 to Complete December
access_time November 10 2025 08:38 PM remove_red_eye 215
Reported by Folmer | Translated by
Reported by Folmer | Translated by
Water channel normalization on Jalan Karet Pasar Baru Barat 1, RT 04/06, Karet Tengsin, Tanah Abang run by Central Jakarta Water Resources Sub-agency personnel, Saturday (11/8), is targeted for completion in December.
We install new 40x40 cm u-ditch
Head of Tanah Abang District's Water Resources Unit, Eli Menawan Sari said normalization is run since the channel had narrowed, causing water to frequently overflow during heavy rain.
Sunter River C Being Dredged as a Flood Prevention Measure"We install new 40x40 cm u-ditch. The work is targeted for completion in 45 days," she said, Monday (11/10).
Alfian (34), a local resident, appreciated the Central Jakarta Water Resources Sub-agency for responding to the residents' request.