Channel Normalization on Jalan Karet Pasar Baru Barat 1 to Complete December

Water channel normalization on Jalan Karet Pasar Baru Barat 1, RT 04/06, Karet Tengsin, Tanah Abang run by Central Jakarta Water Resources Sub-agency personnel, Saturday (11/8), is targeted for completion in December.

We install new 40x40 cm u-ditch

Head of Tanah Abang District's Water Resources Unit, Eli Menawan Sari said normalization is run since the channel had narrowed, causing water to frequently overflow during heavy rain.

Sunter River C Being Dredged as a Flood Prevention Measure

"We install new 40x40 cm u-ditch. The work is targeted for completion in 45 days," she said, Monday (11/10).

Alfian (34), a local resident, appreciated the Central Jakarta Water Resources Sub-agency for responding to the residents' request.

"Hopefully the channel will be able to flow the water smoothly," he hoped.

Linked News
Popular News indeks
  1. Jakarta Set to Launch Historic Municipal Bonds, Pramono Says

    access_time01-07-2026 remove_red_eye1114 personDessy Suciati
  2. Night at The Library Marks Jakarta's 499th Anniversary with Five-Century Message

    access_time27-06-2026 remove_red_eye774 personAnita Karyati
  3. Transportation Agency Teams Up with Ride-Hailing Driver Communities to Promote Road Safety

    access_time27-06-2026 remove_red_eye667 personAldi Geri Lumban Tobing
  4. Jakarta Primed for Transformation into a World-Class Global Hub

    access_time28-06-2026 remove_red_eye628 personDessy Suciati
  5. Jakarta Government Quickly Addresses Toddler Falling into a Hole Incident

    access_time29-06-2026 remove_red_eye621 personDessy Suciati