Utility Works Cause Traffic Diversion on Jalan Jenderal Gatot Subroto

The Jakarta Transportation Agency (Dishub) is detouring a traffic flow on Jalan Jenderal Gatot Subroto, South Jakarta, in connection with Telkom utility network work.

The work site is on the north side of Jalan Jenderal Gatot Subroto

Jakarta Transportation Agency (Dishub) Head, Syafrin Liputo said, utility network work will be ongoing from November 24 to December 8, 2025.

"The work site is on the north side of Jalan Jenderal Gatot Subroto, from the Denpasar Transjakarta Bus Stop to just before Jalan Denpasar," he expressed, Friday (11/28).

Construction Quality and Supervision Must Be Tightened for Mutiara Dam Repairs

He explained, reduction or narrowing of the road body will occur during the construction work. Additionally, the Transjakarta separator, approximately 350 meters long, will be torn down, to optimize lane consistency.

"Thus, the Transjakarta bus becomes mixed traffic and is reinstalled after the work is completed," he explained.

To support the work, traffic engineering is carried out according to the work stages, as follows:

a. Pit 1 Work

1. The excavation point is on the left side of the regular lane next to the Transjakarta Denpasar Bus Stop

2. Work will commence on November 24, 2025, at 10 AM until December 1, 2025, at 4 AM

3. During the work, there will be a reduction in the width of the road

b. Pit 2 Work

1. The excavation point is on the left side of the regular lane in front of the Patra Jasa building (HDD machine)

2. The work will start on November 26, 2025, and end on December 5, 2025

During the work, there will be a reduction in the road width

c. Pit 3 Work

1. The excavation point is on the left side of the regular lane in front of CFX Tower (HDD machine)

2. The work will start from December 6, 2025, to December 14, 2025

3. During the work, there will be a reduction in the road width

d. Pit 4 Work

1. The excavation point is on the left side of the regular lane next to the Kuningan Flyover before Jalan Denpasar (Balai Kartini building)

2. The work will start on December 5, 2025, at 10 PM until December 8, 2025, at 4 AM

3. During the work, there will be a reduction in road width

"Work at pit 1 and pit 4 is only done on holidays or weekends," he stated.

Linked News
Popular News indeks
  1. Cilandak Drainage Upgraded to Mitigate Flooding

    access_time27-01-2026 remove_red_eye866 personTiyo Surya Sakti
  2. TransJabodetabek Expansion, a Strategic Step to Increase Public Transportation Use

    access_time26-01-2026 remove_red_eye422 personFakhrizal Fakhri
  3. Jakarta Prepares OMC and 200 Excavators to Prevent Flood

    access_time26-01-2026 remove_red_eye369 personDessy Suciati
  4. Jakarta Showers to Make Way for Partly Cloudy Skies

    access_time30-01-2026 remove_red_eye354 personDessy Suciati
  5. Several Microtrans Routes Diverted

    access_time31-01-2026 remove_red_eye348 personAldi Geri Lumban Tobing
close