Jalan Layang di Kebayoran Baru Rampung 22,27 Persen

Flyover Project in Kebayoran Baru Reached 22.27 Percent

The Transjakarta corridor XIII Ciledug - Kapten P Tendean flyover development keeps accelerated, especially around Taman Puring, Kebayoran Baru, South Jakarta. Box girder lifting will be done this month.

The contractor will lift the box girder this mid-September

"The contractor will lift the box girder this mid-September," said Heru Suwondo, Head of Overpass and Intersection for Jakarta Bina Marga, Tuesday (9/8).

According to him, the flyover development has reached 22.27 percent out of target 18.39 percent.

Ciledug-Tendean Flyover Construction Has Reached 22 Percent

"I hope other contractors for other flyover packages will do the same thing," he stated.

Linked News
Popular News indeks
  1. Volcanic Ash Reaches Jakarta, Health Agency Calls for Protective Measures

    access_time06-09-2026 remove_red_eye1471 personBudhi Firmansyah Surapati
  2. Jakartans Urged to Stay Calm and Take Precautions Amid Mt. Anak Krakatau Volcanic Ash

    access_time06-09-2026 remove_red_eye747 personBudhi Firmansyah Surapati
  3. Jakarta Provincial Government Anticipates the Impact of Volcanic Ash from Mount Anak Krakatau

    access_time06-09-2026 remove_red_eye613 personFolmer
  4. Jakarta BPBD Urges Residents to Prepare for Meteorological Drought

    access_time04-09-2026 remove_red_eye554 personAldi Geri Lumban Tobing
  5. Pramono Emphasizes Importance of Creative Spaces for Children

    access_time03-09-2026 remove_red_eye474 personDessy Suciati