Jalan Layang di Kebayoran Baru Rampung 22,27 Persen
.
photo istimewa - Beritajakarta.id

Flyover Project in Kebayoran Baru Reached 22.27 Percent

The Transjakarta corridor XIII Ciledug - Kapten P Tendean flyover development keeps accelerated, especially around Taman Puring, Kebayoran Baru, South Jakarta. Box girder lifting will be done this month.

The contractor will lift the box girder this mid-September

"The contractor will lift the box girder this mid-September," said Heru Suwondo, Head of Overpass and Intersection for Jakarta Bina Marga, Tuesday (9/8).

According to him, the flyover development has reached 22.27 percent out of target 18.39 percent.

Ciledug-Tendean Flyover Construction Has Reached 22 Percent

"I hope other contractors for other flyover packages will do the same thing," he stated.

Linked News
Popular News indeks
  1. Commission D Legislator Supports Park Monitoring Optimization

    access_time20-01-2025 remove_red_eye1561 personDessy Suciati
  2. Realizing Food Self-Sufficiency, Jakarta Holds Simultaneous Planting Activity

    access_time21-01-2025 remove_red_eye972 personAldi Geri Lumban Tobing
  3. Long Holidays will Be More Exciting with Rawa Belong Bandeng Festival

    access_time25-01-2025 remove_red_eye587 personAldi Geri Lumban Tobing
  4. Gulkarmat to Intensify Fire Mitigation Education

    access_time22-01-2025 remove_red_eye510 personBudhi Firmansyah Surapati
  5. BMKG Warns of Potential High Rainfall in Jakarta

    access_time22-01-2025 remove_red_eye473 personDessy Suciati