Flood Anticipation, Jalan Ampera VII Concreted

North Jakarta Bina Marga Sub-Department has completed concrete project on Jalan Ampera VII, Pademangan Barat Urban Village, Pademangan. As the road had always been flooded during rainy season for years.

The concrete is more stronger and lasting longer

The road concrete with length about 830 m and width 8 m done by PT Ambalat Jaya Abadi has been completed in a week of the target 45 days. Now the road height increased up to 25 cm.

Head of North Jakarta Bina Marga Sub-Department, Warsito stated that this year there are 58 packets of road elevation with concrete ongoing in his area. Predictably, the project will be done by the end of this year

Puddles in Cilandak Predicted to Be Reduced

"The concrete is more stronger and lasting longer," he stated, Sunday (10/25).

Pademangan Barat Urban Village Forum Institute (LMK) appreciates positively upon the completed concrete project on the road. Considering, the road elevation makes residents not worried about doing activity when rainy season.

"In rainy season the road was always flooded as the road position is paralell with water channel," said Head of Pademangan Barat LMK, Andi Noviriandi.

The member of Pademangan Barat LMK, Edison S Sinambela added that in future water channels in the area proposed to be normalized so that it would not be flooded anymore.

Linked News
Popular News indeks
  1. BMKG: Sunny to Cloudy Skies Forecast Across Jakarta Today

    access_time11-09-2026 remove_red_eye1652 personDessy Suciati
  2. Jakarta Reallocates Funds for Rp 250M Suckermouth Catfish Study After Pramono’s Direct Order

    access_time10-09-2026 remove_red_eye664 personFakhrizal Fakhri
  3. Jakarta Swift Response to Volcanic Ash Helps Narrow Areas with High PM10

    access_time08-09-2026 remove_red_eye467 personAldi Geri Lumban Tobing
  4. Pramono Urges Jakmania to Keep Jakarta Safe

    access_time11-09-2026 remove_red_eye419 personDessy Suciati
  5. Ketapang TPS 3R Processes 13 Tons of Waste from Duri Pulo and Petojo Utara

    access_time11-09-2026 remove_red_eye385 personFolmer