Ciledug - Tendean Flyover Construction Has Touched 35 Percent
Reported by Izzudin | Translated by Trias Risangayu
The construction of Transjakarta
corridor XIII Ciledug - Kapten P Tendean flyover has touched 35 percent. This
progress exceeding the target that had been set by 32 percent.
As this construction apply multiyear system thus it is hoped those 8 work packages could be finished on schedule
Preventing Contra Flow, MCB on Pertama Hijau Flyover Multiplied
Head of City Bina Marga's Road and
Intersection Department, Agus Indroyono stated
the construction itself divided into 8 construction packages with time
execution by 661 days. A 9.3 kilometers flyover construction has been running
from February 2015 and targeted to be done in 2016 December.
“As this
construction apply multiyear system thus it is hoped those 8 work packages could
be finished on schedule” he expressed, Wednesday (12/2).
However,
box girder has begun installed around Mampang Prapatan, Kebayoran Lama, Taman
Puring, and Seskoal.
Responding
the congestion caused by this construction, he admitted that he was working so
hard on it to parse the congestion by coordinating with Police also Jakarta
Transportation Department.