Pembangunan Jalan Layang Ciledug Tendean Mencapai 35 Persen

Ciledug - Tendean Flyover Construction Has Touched 35 Percent

The construction of Transjakarta corridor XIII Ciledug - Kapten P Tendean flyover has touched 35 percent. This progress exceeding the target that had been set by 32 percent.

As this construction apply multiyear system thus it is hoped those 8 work packages could be finished on schedule

Preventing Contra Flow, MCB on Pertama Hijau Flyover Multiplied

Head of City Bina Marga's Road and Intersection Department, Agus Indroyono stated the construction itself divided into 8 construction packages with time execution by 661 days. A 9.3 kilometers flyover construction has been running from February 2015 and targeted to be done in 2016 December.

“As this construction apply multiyear system thus it is hoped those 8 work packages could be finished on schedule” he expressed, Wednesday (12/2).

However, box girder has begun installed around Mampang Prapatan, Kebayoran Lama, Taman Puring, and Seskoal.

Responding the congestion caused by this construction, he admitted that he was working so hard on it to parse the congestion by coordinating with Police also Jakarta Transportation Department.

Linked News
Popular News indeks
  1. MRT Jakarta Integrates Ticket Payments with JakLingko from October 12

    access_time10-10-2026 remove_red_eye537 personAldi Geri Lumban Tobing
  2. Jakarta Administration Steps Up Proactive Fire Prevention Efforts

    access_time09-10-2026 remove_red_eye535 personDessy Suciati
  3. New Kelapa Gading-Pulogadung Road to Ease Traffic and Improve Access

    access_time10-10-2026 remove_red_eye529 personAldi Geri Lumban Tobing
  4. Kramat Pulo Fire Survivors Get Help Replacing School Documents

    access_time09-10-2026 remove_red_eye516 personFolmer
  5. Basic Supplies Distributed to Pinang Ranti Fire Survivors

    access_time09-10-2026 remove_red_eye506 personNurito