 Pembangunan Jalan Layang Tendean Ciledug Sesuai Rencana

Ciledug-Tendean Flyover Construction Is Right on Plan

Until this mid-October, the flyover work for Transjakarta bus lane plying corridor XII (Ciledug-Kapten P Tendean) is running well in accordance with Jakarta Bina Marga Department's plan.

We can tackle constraint well so far. So it doesn’t interfere the project work

Heru Suwondo, Head of Jakarta Bina Marga's Overpass and Intersection Department said that some packages bored pile construction has been completed and is currently working on its column.

Congestion Along Ciledug-Tendean Getting Worse

He appreciates the project operator, PT Adhi Karya, which has tackled constraints well in the field, including the panel box on Jalan Tendean that will be moved.

"We can tackle constraint well so far. So it doesn’t interfere the project work," he uttered, Tuesday (10/13).

Regarding traffic jam affected such project, his side would parse it soon by coordinating with police and Jakarta Transportation Department.

 

 

Linked News
Popular News indeks
  1. Indonesia-Singapore Match: 80 Dishub Personnel Deployed to Manage Traffic Around GBK

    access_time25-09-2026 remove_red_eye722 personAldi Geri Lumban Tobing
  2. Jakarta International Stadium Sets Up Transit Schemes for The Weeknd Concert

    access_time24-09-2026 remove_red_eye522 personAldi Geri Lumban Tobing
  3. Pramono: Climate Action Must Deliver Tangible Benefits to Residents

    access_time25-09-2026 remove_red_eye351 personDessy Suciati
  4. Jakarta Inspectorate Partners with KPK to Foster Early Anti-Corruption Culture

    access_time20-09-2026 remove_red_eye322 personFolmer
  5. Ready for an Island Getaway? Join Us at Maritime Festival 2026 on Kelapa Island!

    access_time20-09-2026 remove_red_eye276 personAnita Karyati