 Normalisasi Saluran Di Dua Kecamatan Tidak Sesuai Target

Channel Normalization Projects in S. Jakarta Faced Many Problems

A number of channel normalization projects which were carried out in several areas in South Jakarta seemed facing problem. This is because the third party who carried out the project has not met any specification.

The worst condition seen on Jalan Mubarok and Permata  Hijau

Head of South Jakarta Water Management, Deddy Budiwidodo mentioned the projects are located on Jalan Mubarok, Permata Hijau, Kebayoran Lama and also Jalan Cibulan, Kebayoran Baru.

“The worst condition is seen on Jalan Mubarok and Permata  Hijau. The contractor performed dredging work with different equipment, while another problem is located on Jalan Cibulan due to being neglected,” he remarked.

Bad Working Performance, 2 Contractors Blacklisted

Whereas, the project carried out on Jalan Cibulan is worth Rp 4.6 billion. “Indeed many problems occurred,” he regretted.

Budiwidodo conveyed that his party has warned the contractor to finish their work completely in accordance with contract agreement.

“We’ve appealed them. The problem mostly occurred in utility and excavation matter,” he closed.

Linked News
Popular News indeks
  1. Jakarta Council Begins Deliberations on New Population and Housing Bylaws

    access_time21-08-2026 remove_red_eye1885 personFakhrizal Fakhri
  2. Pramono Vows to Prioritize Jakarta’s Strategic Development

    access_time22-08-2026 remove_red_eye857 personDessy Suciati
  3. Pramono Commends Madurese Community for Their Vital Role in Building Jakarta

    access_time19-08-2026 remove_red_eye681 personDessy Suciati
  4. Pramono Pushes for Partnership Between New Toto Tentrem and Tarakan Hospitals

    access_time24-08-2026 remove_red_eye473 personDessy Suciati
  5. New LRT Jakarta Route Set for Official Launch on August 26

    access_time22-08-2026 remove_red_eye447 personDessy Suciati