Pembangunan Jalan Layang Transjakarta Capai 54 Persen

Elevated Transjakarta Lane Project Reaches 54 Percent

The construction of elevated Transjakarta corridor XIII Tendean-Ciledug, as long as 9.3 km, has reached 54.6 percent. It is targeted the project to finish in December 2016.

54.6 percent is total progress from last year up to today. So far so good

“54.6 percent is total progress from last year up to today. So far so good,” said Yusmada Faizal, Jakarta Head Dept. of Bina Marga, Monday (3/14).

According to him, some spots have started to install box girder. He is optimistic the project would finish on time even though there is still problem on land buying process in some locations.

Damaged Road Impacted by Corridor XIII Repaired

Yusmada will request developer to construct escalator in each shelter of Transjakarta corridor XIII. Based on early design, pedestrian bridge is still using stairs.

“The fund is taken from developer. They also maintain and operate the escalator,” he added.

Linked News
Popular News indeks
  1. Jakarta Claims Rp 2.27 T in Public Assets from Developer Obligations

    access_time06-08-2026 remove_red_eye740 personDessy Suciati
  2. New LapakMain Corner Creative Hub Inaugurated at Tunas Muda RPTRA, Kramat Pela

    access_time05-08-2026 remove_red_eye620 personTiyo Surya Sakti
  3. Abdul Muis Building Fire Response Nears Completion, No Fatalities Reported

    access_time08-08-2026 remove_red_eye567 personAldi Geri Lumban Tobing
  4. Jakarta Ensures Public Services Stay Operational After Abdul Muis Building Fire

    access_time08-08-2026 remove_red_eye528 personFakhrizal Fakhri
  5. Jakarta Remains Indonesia's Top Investment Destination

    access_time07-08-2026 remove_red_eye505 personAldi Geri Lumban Tobing