Pembangunan Jalan Layang Transjakarta Capai 54 Persen

Elevated Transjakarta Lane Project Reaches 54 Percent

The construction of elevated Transjakarta corridor XIII Tendean-Ciledug, as long as 9.3 km, has reached 54.6 percent. It is targeted the project to finish in December 2016.

54.6 percent is total progress from last year up to today. So far so good

“54.6 percent is total progress from last year up to today. So far so good,” said Yusmada Faizal, Jakarta Head Dept. of Bina Marga, Monday (3/14).

According to him, some spots have started to install box girder. He is optimistic the project would finish on time even though there is still problem on land buying process in some locations.

Damaged Road Impacted by Corridor XIII Repaired

Yusmada will request developer to construct escalator in each shelter of Transjakarta corridor XIII. Based on early design, pedestrian bridge is still using stairs.

“The fund is taken from developer. They also maintain and operate the escalator,” he added.

Linked News
Popular News indeks
  1. 129 Motorcycle Parked Illegally in Daan Mogot Controlled

    access_time08-11-2026 remove_red_eye708 personBudhi Firmansyah Surapati
  2. Kampung Melayu Sports Facility Inaugurated to Tackle Brawls

    access_time06-11-2026 remove_red_eye668 personDessy Suciati
  3. Jakarta to Develop Its First Mangrove Botanical Garden

    access_time06-11-2026 remove_red_eye666 personDessy Suciati
  4. Aid for Fire Survivors at Pinus Elok Flats Has Been Distributed

    access_time06-11-2026 remove_red_eye633 personNurito
  5. Kampung Rambutan 1 Reservoir to Combine Flood Control with Public Recreation

    access_time06-11-2026 remove_red_eye629 personAldi Geri Lumban Tobing