Pembangunan Jalan Layang Transjakarta Capai 54 Persen

Elevated Transjakarta Lane Project Reaches 54 Percent

The construction of elevated Transjakarta corridor XIII Tendean-Ciledug, as long as 9.3 km, has reached 54.6 percent. It is targeted the project to finish in December 2016.

54.6 percent is total progress from last year up to today. So far so good

“54.6 percent is total progress from last year up to today. So far so good,” said Yusmada Faizal, Jakarta Head Dept. of Bina Marga, Monday (3/14).

According to him, some spots have started to install box girder. He is optimistic the project would finish on time even though there is still problem on land buying process in some locations.

Damaged Road Impacted by Corridor XIII Repaired

Yusmada will request developer to construct escalator in each shelter of Transjakarta corridor XIII. Based on early design, pedestrian bridge is still using stairs.

“The fund is taken from developer. They also maintain and operate the escalator,” he added.

Linked News
Popular News indeks
  1. Indonesia-Singapore Match: 80 Dishub Personnel Deployed to Manage Traffic Around GBK

    access_time25-09-2026 remove_red_eye1123 personAldi Geri Lumban Tobing
  2. Jakarta International Stadium Sets Up Transit Schemes for The Weeknd Concert

    access_time24-09-2026 remove_red_eye833 personAldi Geri Lumban Tobing
  3. Pramono: Climate Action Must Deliver Tangible Benefits to Residents

    access_time25-09-2026 remove_red_eye541 personDessy Suciati
  4. Pasar Baru Rowing Race Set to Take Place This Sunday

    access_time25-09-2026 remove_red_eye507 personFolmer
  5. Kelapa Gading-Manggarai LRT Serves 100,343 Passengers

    access_time26-09-2026 remove_red_eye479 personAldi Geri Lumban Tobing