Pembangunan Jalan Layang Transjakarta Capai 54 Persen

Elevated Transjakarta Lane Project Reaches 54 Percent

The construction of elevated Transjakarta corridor XIII Tendean-Ciledug, as long as 9.3 km, has reached 54.6 percent. It is targeted the project to finish in December 2016.

54.6 percent is total progress from last year up to today. So far so good

“54.6 percent is total progress from last year up to today. So far so good,” said Yusmada Faizal, Jakarta Head Dept. of Bina Marga, Monday (3/14).

According to him, some spots have started to install box girder. He is optimistic the project would finish on time even though there is still problem on land buying process in some locations.

Damaged Road Impacted by Corridor XIII Repaired

Yusmada will request developer to construct escalator in each shelter of Transjakarta corridor XIII. Based on early design, pedestrian bridge is still using stairs.

“The fund is taken from developer. They also maintain and operate the escalator,” he added.

Linked News
Popular News indeks
  1. Nighttime Surveillance on Railroad Banks of Jalan I Gusti Ngurah Rai Intensified

    access_time08-05-2026 remove_red_eye2614 personNurito
  2. Governor Pram Appreciates Residents for Keeping Jakarta Safe and Comfortable

    access_time09-05-2026 remove_red_eye949 personFolmer
  3. PSEL Project to Solve Jakarta's Waste Crisis, Says Pramono

    access_time06-05-2026 remove_red_eye907 personDessy Suciati
  4. Jakarta`s 499th Anniversary and a Waste Sorting Movement Launched

    access_time10-05-2026 remove_red_eye685 personTiyo Surya Sakti
  5. CFD will Be Held on Jalan HR Rasuna Said

    access_time08-05-2026 remove_red_eye622 personDessy Suciati