Pembangunan Jalan Layang Transjakarta Capai 54 Persen

Elevated Transjakarta Lane Project Reaches 54 Percent

The construction of elevated Transjakarta corridor XIII Tendean-Ciledug, as long as 9.3 km, has reached 54.6 percent. It is targeted the project to finish in December 2016.

54.6 percent is total progress from last year up to today. So far so good

“54.6 percent is total progress from last year up to today. So far so good,” said Yusmada Faizal, Jakarta Head Dept. of Bina Marga, Monday (3/14).

According to him, some spots have started to install box girder. He is optimistic the project would finish on time even though there is still problem on land buying process in some locations.

Damaged Road Impacted by Corridor XIII Repaired

Yusmada will request developer to construct escalator in each shelter of Transjakarta corridor XIII. Based on early design, pedestrian bridge is still using stairs.

“The fund is taken from developer. They also maintain and operate the escalator,” he added.

Linked News
Popular News indeks
  1. Jakarta Council Begins Deliberations on New Population and Housing Bylaws

    access_time21-08-2026 remove_red_eye1933 personFakhrizal Fakhri
  2. Pramono Vows to Prioritize Jakarta’s Strategic Development

    access_time22-08-2026 remove_red_eye1027 personDessy Suciati
  3. Rano: CIEIE 2026 to Catapult Jakarta’s MSMEs onto the International Stage

    access_time25-08-2026 remove_red_eye722 personBudhi Firmansyah Surapati
  4. Pramono Pushes for Partnership Between New Toto Tentrem and Tarakan Hospitals

    access_time24-08-2026 remove_red_eye646 personDessy Suciati
  5. Jakarta Deploys 120 Personnel to Counteract Traffic Disruption for Today’s Protests

    access_time27-08-2026 remove_red_eye547 personAldi Geri Lumban Tobing