The execution of illegal buildings along Kali Beton riverbank, Taman Sari sub-district, remains continued. As many as five buildings entering Taman Sari Urban Village and Maphar Urban Village, Taman Sari, were controlled.
Last week, the execution was postponed since RT caretaker was ready to demolish its post
Taman Sari Sub-district Head, Paris Limbong, said the execution was done by PPSU and Satpol PP personnel. One heavy equipment was deployed to ease execution.
“Last week, the execution was postponed since RT caretaker was ready to demolish its post. Unfortunately, he lied. So we have to execute the buildings today,” he said, Wednesday (4/20).
15 Stalls in Taman Sari Torn DownHis side also executed buildings in Maphar Urban Village. Those are Posyantek and building used as warehouse.