Progres Pembangunan Flyover Latumenten Capai 63 Persen

Latumenten Flyover Construction Progress Reaches 63 Percent

Entering its 40th week, construction of the Latumenten Flyover in Grogol, West Jakarta, has reached 63 percent completion. One of the most crucial tasks, girder erection at the railway crossing, has been completed.

Improve transportation connectivity

In addition to these works, construction is also continuing on a number of other components, including the pedestrian bridge (JPO) borepile, spun pile and pilehead, pier, bridge plate, barrier, installation of PCU girder, elastomeric runway, construction of skywalk, and Transjakarta bus stop which will later be integrated with Grogol Station.

Equipped with Elevators, Ciracas GOR Pedestrian Bridge Infused with Betawi Heritage

The Head of the Data and Information Center of the Jakarta Public Works Agency, Siti Dinarwenny, said that this achievement shows that the work is progressing according to the planned stages, including the completion of girder erection in the railway crossing area.

"The girder erection process at a railway crossing is a highly complex process. All work is carried out through careful planning and strict supervision, prioritizing safety, security, and construction accuracy," she said, Thursday (7/30).

Wenny explained that the Latumeten Flyover provides various benefits for the community, starting from improving safety by eliminating the railway level crossing, reducing traffic congestion in the West Jakarta area, facilitating intermodal transfers through connectivity between the Transjakarta Bus Stop and Grogol Station, to supporting the smooth operation of train travel.

"The Latumeten Flyover is built as part of the Jakarta Provincial Government's efforts to improve transportation connectivity and overcome traffic jams that have occurred due to the railway level crossing in the area," she explained.

As for information, the Latumenten Flyover infrastructure consists of two spans. The Slipi-bound stretch is approximately 435 meters long and 11 meters wide, while the Grogol-bound stretch is approximately 420 meters long and the same width. Each stretch features two lanes for public transportation and one busway lane. Construction of the flyover is targeted for completion by December 15, 2026.

Linked News
Popular News indeks
  1. Commission E Enlists Religious Leaders to Fight Drugs and Violence

    access_time24-07-2026 remove_red_eye1281 personFakhrizal Fakhri
  2. Jakarta Government Prepares Rp 249 B to Renovate Four Schools

    access_time25-07-2026 remove_red_eye864 personDessy Suciati
  3. 20 Shade Trees Planted on Jalan Komodor Halim Perdanakusuma

    access_time24-07-2026 remove_red_eye799 personNurito
  4. Transjakarta Officially Commences Jakarta Batavia Open-Top Bus Service

    access_time24-07-2026 remove_red_eye798 personBudhi Firmansyah Surapati
  5. Rano Urges Jakarta Scouts to Be Active in Waste Sorting Movement

    access_time25-07-2026 remove_red_eye671 personAldi Geri Lumban Tobing