Pembangunan Simpang Susun Semanggi Capai 20 Persen

Semanggi Interchanges Project Has Reached 20 Percent

Insha Allah, it will be complete on time

The Semanggi interchanges construction until now has reached 20 percent. It is targeted to be complete in August 2017.

Head of Jakarta Bina Marga Dept, Yusmada Faizal disclosed, foundation construction is completed. And pole has been entered installation project. "The project has reached 20 percent," he stated, at City Hall, Tuesday (9/20).

Semanggi Interchange Project Begins

He added, it takes over 540 days. It consists of 60 days of planning and 480 days of execution or about 18 months ahead. "Insha Allah, it will be complete on time," he told.

There have been two lanes, namely from Grogol to Blok M along 796 meters and Polda to Monas along 826 meters. It is hoped able to parse traffic jam.

Fund for lane construction amounting to Rp 360 billion is from Japanese company, Mori Company, that is PT Mitra Panca Persada. In details, physical project Rp 345 billion and consultant cost Rp 15 billion. While the contractor is PT Wijaya Karya (Wika).

Linked News
Popular News indeks
  1. Jakarta Removes Gibran’s Portraits Across All Government Offices

    access_time16-11-2026 remove_red_eye988 personFakhrizal Fakhri
  2. Transjakarta Offers Free Rides for Jakarta Vertical Run 2026 Participants

    access_time14-11-2026 remove_red_eye645 personAldi Geri Lumban Tobing
  3. Governor Approves Removal of Seven Unauthorized Houses on Dispora Land

    access_time13-11-2026 remove_red_eye618 personFakhrizal Fakhri
  4. Pramono Outlines Measures to Address Five Issues in Kramat Jati

    access_time13-11-2026 remove_red_eye605 personFakhrizal Fakhri
  5. Jakarta Esports 2026 Draws Enthusiastic Crowds at M Bloc Space

    access_time13-11-2026 remove_red_eye575 personTiyo Surya Sakti