Pembangunan Simpang Susun Semanggi Capai 20 Persen

Semanggi Interchanges Project Has Reached 20 Percent

Insha Allah, it will be complete on time

The Semanggi interchanges construction until now has reached 20 percent. It is targeted to be complete in August 2017.

Head of Jakarta Bina Marga Dept, Yusmada Faizal disclosed, foundation construction is completed. And pole has been entered installation project. "The project has reached 20 percent," he stated, at City Hall, Tuesday (9/20).

Semanggi Interchange Project Begins

He added, it takes over 540 days. It consists of 60 days of planning and 480 days of execution or about 18 months ahead. "Insha Allah, it will be complete on time," he told.

There have been two lanes, namely from Grogol to Blok M along 796 meters and Polda to Monas along 826 meters. It is hoped able to parse traffic jam.

Fund for lane construction amounting to Rp 360 billion is from Japanese company, Mori Company, that is PT Mitra Panca Persada. In details, physical project Rp 345 billion and consultant cost Rp 15 billion. While the contractor is PT Wijaya Karya (Wika).

Linked News
Popular News indeks
  1. Cilandak Drainage Upgraded to Mitigate Flooding

    access_time27-01-2026 remove_red_eye869 personTiyo Surya Sakti
  2. TransJabodetabek Expansion, a Strategic Step to Increase Public Transportation Use

    access_time26-01-2026 remove_red_eye424 personFakhrizal Fakhri
  3. Jakarta Prepares OMC and 200 Excavators to Prevent Flood

    access_time26-01-2026 remove_red_eye371 personDessy Suciati
  4. Jakarta Showers to Make Way for Partly Cloudy Skies

    access_time30-01-2026 remove_red_eye359 personDessy Suciati
  5. Several Microtrans Routes Diverted

    access_time31-01-2026 remove_red_eye358 personAldi Geri Lumban Tobing
close