Pembangunan Simpang Susun Semanggi Capai 20 Persen

Semanggi Interchanges Project Has Reached 20 Percent

Insha Allah, it will be complete on time

The Semanggi interchanges construction until now has reached 20 percent. It is targeted to be complete in August 2017.

Head of Jakarta Bina Marga Dept, Yusmada Faizal disclosed, foundation construction is completed. And pole has been entered installation project. "The project has reached 20 percent," he stated, at City Hall, Tuesday (9/20).

Semanggi Interchange Project Begins

He added, it takes over 540 days. It consists of 60 days of planning and 480 days of execution or about 18 months ahead. "Insha Allah, it will be complete on time," he told.

There have been two lanes, namely from Grogol to Blok M along 796 meters and Polda to Monas along 826 meters. It is hoped able to parse traffic jam.

Fund for lane construction amounting to Rp 360 billion is from Japanese company, Mori Company, that is PT Mitra Panca Persada. In details, physical project Rp 345 billion and consultant cost Rp 15 billion. While the contractor is PT Wijaya Karya (Wika).

Linked News
Popular News indeks
  1. Pram-Rano Attend Bung Karno Festival at Proklamasi Park

    access_time20-06-2026 remove_red_eye1088 personFolmer
  2. JIS-Ancol Integrated Infrastructure Officially Activated

    access_time23-06-2026 remove_red_eye571 personDessy Suciati
  3. Free Cake-Making Training Held at RPTRA Mustika Ratu

    access_time23-06-2026 remove_red_eye489 personNurito
  4. Metropolitan City Rally 2026 to Be Held at City Hall

    access_time19-06-2026 remove_red_eye473 personAldi Geri Lumban Tobing
  5. Rano Officially Opens Discover Betawi Art and Culture 2026

    access_time19-06-2026 remove_red_eye470 personBudhi Firmansyah Surapati