Pembangunan Simpang Susun Semanggi Capai 20 Persen

Semanggi Interchanges Project Has Reached 20 Percent

Insha Allah, it will be complete on time

The Semanggi interchanges construction until now has reached 20 percent. It is targeted to be complete in August 2017.

Head of Jakarta Bina Marga Dept, Yusmada Faizal disclosed, foundation construction is completed. And pole has been entered installation project. "The project has reached 20 percent," he stated, at City Hall, Tuesday (9/20).

Semanggi Interchange Project Begins

He added, it takes over 540 days. It consists of 60 days of planning and 480 days of execution or about 18 months ahead. "Insha Allah, it will be complete on time," he told.

There have been two lanes, namely from Grogol to Blok M along 796 meters and Polda to Monas along 826 meters. It is hoped able to parse traffic jam.

Fund for lane construction amounting to Rp 360 billion is from Japanese company, Mori Company, that is PT Mitra Panca Persada. In details, physical project Rp 345 billion and consultant cost Rp 15 billion. While the contractor is PT Wijaya Karya (Wika).

Linked News
Popular News indeks
  1. Jakarta Government Guarantees Full Medical Care for Bantargebang Landslide Victims

    access_time09-03-2026 remove_red_eye1296 personDessy Suciati
  2. Commission E Supports Restricting Children's Access to Social Media

    access_time09-03-2026 remove_red_eye1127 personFakhrizal Fakhri
  3. Affordable and High-Quality Staple Goods Offered at Ramadan Bazaar

    access_time09-03-2026 remove_red_eye838 personAldi Geri Lumban Tobing
  4. Jakarta Planetarium Rolls Out Varied Shows for Eid al-Fitr Holiday

    access_time11-03-2026 remove_red_eye290 personAldi Geri Lumban Tobing
  5. Jakarta Speeds Up Flood Mitigation Efforts

    access_time08-03-2026 remove_red_eye288 personAldi Geri Lumban Tobing