Land Buying Obstructs Pondok Ranggon 1 Reservoir Construction
access_time September 22 2016 02:16 PM remove_red_eye 1522
Reported by Nurito | Translated by Rizky Mawardi
Reported by Nurito | Translated by Rizky Mawardi
The construction of Pondok Ranggon 1 and 2 Reservoir is targeted to complete by this year. In fact, not all land are already bought.
3,412 meter square is divided into 16 lots. Seven of them have buildings above it
Pondok Ranggon 1 reservoir leaves 16 land lots by 3,412 meter square. The remaining 2,371 meter square are being inventoried.
Pondok Ranggon Urban Village Head, Mahpuz MZ, admitted the land buying process for Pondok Ranggon 1 has been started since 2006 ago. It is planned that the reservoir has total width by 11.5 hectares.
Rambutan 1 Reservoir Project Needs Additional Equipmentβ3,412 meter square is divided into 16 lots. Seven of them have buildings above it,β he said, Thursday (9/22).
Asep Setia Permana, Jakarta Staff of River and Beach for East Flow for Dept. of Water Management, said his side is cooperating with Mabes TNI to deploy the heavy equipment. It is impossible to deploy the equipments via settlement road.
βThe only access is via Mabes TNI,β he said.