Alat Berat Minim, Pembangunan Waduk Rambutan Diprediksi Molor

Rambutan 1 Reservoir Project Needs Additional Equipment

The Rambutan 1 Reservoir that located at RW 04 and 06 Kampung Rambutan Urban Village, Ciracas needs additional heavy equipment.

The heavy equipment is minimal and the solar supply is constrained. I believe the completion target in December will not be realized

Rambutan 1 Reservoir Project Supervisor, Marudin disclosed, ideally the construction with five hectares wide needs 8-10 heavy equipments. At this time, there have been four units.

"The heavy equipment is minimal and the solar supply is constrained. I believe the completion target in December will not be realized," he stated, Wednesday (9/21).

Damaged Pumps Repair at Bojong Reservoir Takes A Month

If there is additional equipment, his side is optimistic such target could be complete by the end of December using non-stop system. The current dredging only be done from 8.30 AM-4 PM.

"The project itself has been ongoing since three months ago. It is done every day," he told.

Previously, he also has reported on the slow supply of solar that hinder the project.

The needs per day for four heavy equipments is around 480 liters solar. Even it could reach 700 liters solar where the dredging done until 6 PM.

Linked News
Popular News indeks
  1. Water Channel on Jalan SPG 7 Being Improved

    access_time18-09-2026 remove_red_eye800 personNurito
  2. Jakarta Govt Fully Backs Kanye West's Ye Live in Jakarta 2026

    access_time16-09-2026 remove_red_eye534 personDessy Suciati
  3. Jakarta Pushes to Strengthen Food Ecosystem

    access_time18-09-2026 remove_red_eye479 personAldi Geri Lumban Tobing
  4. Pramono Departs for New York to Discuss Climate and Food Crises

    access_time18-09-2026 remove_red_eye412 personDessy Suciati
  5. Operations of the MV Doulos Hope Ship Library Delayed

    access_time18-09-2026 remove_red_eye391 personAnita Karyati