Rambutan 1 Reservoir Project Needs Additional Equipment
Reported by Nurito | Translated by Nugroho Adibrata
The Rambutan 1 Reservoir that located at RW 04 and 06 Kampung Rambutan Urban Village, Ciracas needs additional heavy equipment.
The heavy equipment is minimal and the solar supply is constrained. I believe the completion target in December will not be realized
Rambutan 1 Reservoir Project Supervisor, Marudin disclosed, ideally the construction with five hectares wide needs 8-10 heavy equipments. At this time, there have been four units.
"The heavy equipment is minimal and the solar supply is constrained. I believe the completion target in December will not be realized," he stated, Wednesday (9/21).
Damaged Pumps Repair at Bojong Reservoir Takes A MonthIf there is additional equipment, his side is optimistic such target could be complete by the end of December using non-stop system. The current dredging only be done from 8.30 AM-4 PM.
"The project itself has been ongoing since three months ago. It is done every day," he told.
Previously, he also has reported on the slow supply of solar that hinder the project.
The needs per day for four heavy equipments is around 480 liters solar. Even it could reach 700 liters solar where the dredging done until 6 PM.