Alat Berat Minim, Pembangunan Waduk Rambutan Diprediksi Molor

Rambutan 1 Reservoir Project Needs Additional Equipment

The Rambutan 1 Reservoir that located at RW 04 and 06 Kampung Rambutan Urban Village, Ciracas needs additional heavy equipment.

The heavy equipment is minimal and the solar supply is constrained. I believe the completion target in December will not be realized

Rambutan 1 Reservoir Project Supervisor, Marudin disclosed, ideally the construction with five hectares wide needs 8-10 heavy equipments. At this time, there have been four units.

"The heavy equipment is minimal and the solar supply is constrained. I believe the completion target in December will not be realized," he stated, Wednesday (9/21).

Damaged Pumps Repair at Bojong Reservoir Takes A Month

If there is additional equipment, his side is optimistic such target could be complete by the end of December using non-stop system. The current dredging only be done from 8.30 AM-4 PM.

"The project itself has been ongoing since three months ago. It is done every day," he told.

Previously, he also has reported on the slow supply of solar that hinder the project.

The needs per day for four heavy equipments is around 480 liters solar. Even it could reach 700 liters solar where the dredging done until 6 PM.

Linked News
Popular News indeks
  1. May Day: Transjakarta Service Adjustments

    access_time01-05-2026 remove_red_eye796 personAldi Geri Lumban Tobing
  2. The Lights-Out Action Successfully Reduces Carbon Emissions

    access_time27-04-2026 remove_red_eye561 personAldi Geri Lumban Tobing
  3. MRT Jakarta Urged to Enhance Power Outage Mitigation System

    access_time27-04-2026 remove_red_eye546 personFakhrizal Fakhri
  4. City Deploys Massive Cleanup Force for May Day at Monas

    access_time01-05-2026 remove_red_eye534 personAldi Geri Lumban Tobing
  5. Dinkes Sets Up Health Posts for May Day Events

    access_time01-05-2026 remove_red_eye533 personDessy Suciati