Pembangunan Proyek Simpang Susun Semanggi Mencapai 32 Persen

Semanggi Flyover Project Reaches 32 Percent

The construction of Semanggi flyover keeps accelerated. At this moment, the construction has reached 32 percent. The project is targeted to complete on August 17, 2017.

It started from pole foundation by 17 spots up to erection box for Grogol-Blok M and Cawang-Bundaran HI rings

“Latest progress has reached 32 percent. It started from pole foundation by 17 spots up to erection box for Grogol-Blok M and Cawang-Bundaran HI rings,” said Yusmada Faisal, Jakarta Head Dept. of Bina Marga, Monday (10/24).

He added that the flyover will decrease traffic jam around the area. Vehicles will have their own lane without met with others.

Developer's Additional Obligation Uses for Infrastructure

The project has two rings from Grogol to Blok M along 796 meters and Polda to Monas along 826 meters.

The fund is taken from Japanese company obligation, PT Mitra Panca Persada. It will spend Rp 360 billion In details are Rp 345 billion for physical and Rp 15 billion for consultant. Contractor for this project is PT Wijaya Karya (Wika).

Linked News
Popular News indeks
  1. Central Jakarta Administration Acts Swiftly to Handle Kebon Kosong Fire

    access_time02-06-2026 remove_red_eye1433 personFolmer
  2. Central Jakarta Government Responds Quickly to Fire Victims in Tanah Tinggi

    access_time04-06-2026 remove_red_eye950 personFolmer
  3. Jakarta Waives Motor Vehicle Tax Fines and Title Transfer Fees

    access_time01-06-2026 remove_red_eye864 personAldi Geri Lumban Tobing
  4. Commemorating Vesak, Jakarta Lights Up with Illumination of Jakarta 2026

    access_time30-05-2026 remove_red_eye664 personBudhi Firmansyah Surapati
  5. Seniors Participate in Pasti Bisa Berkarya at MRT Stations

    access_time02-06-2026 remove_red_eye612 personAldi Geri Lumban Tobing