Kinerja Kontraktor IPAL Pulau Seribu Dievaluasi
.
photo Suparni - Beritajakarta.id

IPAL Project on di Panggang Island Stagnated

The waste water treatment plants (IPAL) construction on Panggang Island, Seribu Islands, stagnated.

Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent

It will be stopped if the contractor cannot finish it on December 5, 2016.

IPAL Construction on Panggang Island Accelerated

"Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent," expressed Mustajab, Head of Seribu Islands Water Management Sub-dept, Saturday (12/3).

He went on the say that if they cannot met it, his party will stop the contract. 

"If the contract was stopped, they must fix the excavation and restore it as before," he stated. 

As known, the project has spent Rp 3 billion and was targeted to be finished on December 5. Then another project on Tidung Island has spent Rp 10.2 billion.

Currently, its project has reached 75 percent, and is targeted to be finished in the upcoming December.

Linked News
Popular News indeks
  1. Free Additional Nutritious Food Distributed to 31 Toddlers in Kalibata

    access_time13-09-2024 remove_red_eye1152 personTiyo Surya Sakti
  2. Jakarta Women's Football Team Ready to Face West Java at PON XXI Final

    access_time13-09-2024 remove_red_eye849 personFolmer
  3. Water Channel Dredging on Bendungan Melayu Reaches 50 Percent

    access_time18-09-2024 remove_red_eye828 personAnita Karyati
  4. Jakarta Leads Medal Standing at PON XXI

    access_time17-09-2024 remove_red_eye781 personFolmer
  5. PON XXI Temporary Standings: Jakarta Continues to Shadow East Java

    access_time13-09-2024 remove_red_eye760 personAldi Geri Lumban Tobing