IPAL Project on di Panggang Island Stagnated

The waste water treatment plants (IPAL) construction on Panggang Island, Seribu Islands, stagnated.

Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent

It will be stopped if the contractor cannot finish it on December 5, 2016.

IPAL Construction on Panggang Island Accelerated

"Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent," expressed Mustajab, Head of Seribu Islands Water Management Sub-dept, Saturday (12/3).

He went on the say that if they cannot met it, his party will stop the contract. 

"If the contract was stopped, they must fix the excavation and restore it as before," he stated. 

As known, the project has spent Rp 3 billion and was targeted to be finished on December 5. Then another project on Tidung Island has spent Rp 10.2 billion.

Currently, its project has reached 75 percent, and is targeted to be finished in the upcoming December.

Linked News
Popular News indeks
  1. BMKG: Sunny to Cloudy Skies Forecast Across Jakarta Today

    access_time11-09-2026 remove_red_eye1662 personDessy Suciati
  2. Jakarta Reallocates Funds for Rp 250M Suckermouth Catfish Study After Pramono’s Direct Order

    access_time10-09-2026 remove_red_eye668 personFakhrizal Fakhri
  3. Jakarta Swift Response to Volcanic Ash Helps Narrow Areas with High PM10

    access_time08-09-2026 remove_red_eye469 personAldi Geri Lumban Tobing
  4. Pramono Urges Jakmania to Keep Jakarta Safe

    access_time11-09-2026 remove_red_eye431 personDessy Suciati
  5. Pramono Endorses Five-City Tour for Jazz Goes to Campus

    access_time12-09-2026 remove_red_eye401 personDessy Suciati