IPAL Project on di Panggang Island Stagnated

The waste water treatment plants (IPAL) construction on Panggang Island, Seribu Islands, stagnated.

Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent

It will be stopped if the contractor cannot finish it on December 5, 2016.

IPAL Construction on Panggang Island Accelerated

"Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent," expressed Mustajab, Head of Seribu Islands Water Management Sub-dept, Saturday (12/3).

He went on the say that if they cannot met it, his party will stop the contract. 

"If the contract was stopped, they must fix the excavation and restore it as before," he stated. 

As known, the project has spent Rp 3 billion and was targeted to be finished on December 5. Then another project on Tidung Island has spent Rp 10.2 billion.

Currently, its project has reached 75 percent, and is targeted to be finished in the upcoming December.

Linked News
Popular News indeks
  1. Attending Betawi Eid 2026, Pram Encourages Strengthening Cultural Values

    access_time11-04-2026 remove_red_eye1103 personFolmer
  2. Low Emission Zones: Jakarta’s Concrete Step to Curb Air Pollution

    access_time13-04-2026 remove_red_eye1048 personAldi Geri Lumban Tobing
  3. Jakpro Promotes Integration Between JIS and KRL Station

    access_time10-04-2026 remove_red_eye879 personAldi Geri Lumban Tobing
  4. Cilandak Health Center Maintains Optimal Services

    access_time10-04-2026 remove_red_eye852 personTiyo Surya Sakti
  5. Pademangan Health Center Promotes 3M Plus to Prevent Dengue Fever

    access_time14-04-2026 remove_red_eye755 personAnita Karyati