IPAL Project on di Panggang Island Stagnated

The waste water treatment plants (IPAL) construction on Panggang Island, Seribu Islands, stagnated.

Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent

It will be stopped if the contractor cannot finish it on December 5, 2016.

IPAL Construction on Panggang Island Accelerated

"Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent," expressed Mustajab, Head of Seribu Islands Water Management Sub-dept, Saturday (12/3).

He went on the say that if they cannot met it, his party will stop the contract. 

"If the contract was stopped, they must fix the excavation and restore it as before," he stated. 

As known, the project has spent Rp 3 billion and was targeted to be finished on December 5. Then another project on Tidung Island has spent Rp 10.2 billion.

Currently, its project has reached 75 percent, and is targeted to be finished in the upcoming December.

Linked News
Popular News indeks
  1. Volcanic Ash Reaches Jakarta, Health Agency Calls for Protective Measures

    access_time06-09-2026 remove_red_eye967 personBudhi Firmansyah Surapati
  2. Transjakarta Commits to Accelerating Modal Integration and Fleet Electrification

    access_time31-08-2026 remove_red_eye688 personAldi Geri Lumban Tobing
  3. JITEX 2026: Fostering a Global Trade and Investment Ecosystem

    access_time01-09-2026 remove_red_eye589 personAldi Geri Lumban Tobing
  4. Jakartans Urged to Stay Calm and Take Precautions Amid Mt. Anak Krakatau Volcanic Ash

    access_time06-09-2026 remove_red_eye585 personBudhi Firmansyah Surapati
  5. Jakarta BPBD Urges Residents to Prepare for Meteorological Drought

    access_time04-09-2026 remove_red_eye502 personAldi Geri Lumban Tobing