Kinerja Kontraktor IPAL Pulau Seribu Dievaluasi

IPAL Project on di Panggang Island Stagnated

The waste water treatment plants (IPAL) construction on Panggang Island, Seribu Islands, stagnated.

Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent

It will be stopped if the contractor cannot finish it on December 5, 2016.

IPAL Construction on Panggang Island Accelerated

"Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent," expressed Mustajab, Head of Seribu Islands Water Management Sub-dept, Saturday (12/3).

He went on the say that if they cannot met it, his party will stop the contract. 

"If the contract was stopped, they must fix the excavation and restore it as before," he stated. 

As known, the project has spent Rp 3 billion and was targeted to be finished on December 5. Then another project on Tidung Island has spent Rp 10.2 billion.

Currently, its project has reached 75 percent, and is targeted to be finished in the upcoming December.

Linked News
Popular News indeks
  1. Fire at Pondok Bambu Allegedly Triggered by Electrical Short

    access_time19-05-2026 remove_red_eye1395 personNurito
  2. Governor Pramono Named Vice Chair of C40 Cities Steering Committee

    access_time18-05-2026 remove_red_eye1027 personAldi Geri Lumban Tobing
  3. Kultura Market in Pademangan Barat Attracts Crowds

    access_time22-05-2026 remove_red_eye994 personAnita Karyati
  4. Inundation on DI Panjaitan Road Recede

    access_time20-05-2026 remove_red_eye858 personNurito
  5. Dharma Jaya Ready for Thousands of Eid al-Adha Sacrifices

    access_time20-05-2026 remove_red_eye676 personAldi Geri Lumban Tobing