IPAL Project on di Panggang Island Stagnated

The waste water treatment plants (IPAL) construction on Panggang Island, Seribu Islands, stagnated.

Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent

It will be stopped if the contractor cannot finish it on December 5, 2016.

IPAL Construction on Panggang Island Accelerated

"Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent," expressed Mustajab, Head of Seribu Islands Water Management Sub-dept, Saturday (12/3).

He went on the say that if they cannot met it, his party will stop the contract. 

"If the contract was stopped, they must fix the excavation and restore it as before," he stated. 

As known, the project has spent Rp 3 billion and was targeted to be finished on December 5. Then another project on Tidung Island has spent Rp 10.2 billion.

Currently, its project has reached 75 percent, and is targeted to be finished in the upcoming December.

Linked News
Popular News indeks
  1. Jakarta Announces Rp 1 Fare for Transjakarta, MRT, and LRT on August 17

    access_time13-08-2026 remove_red_eye929 personAldi Geri Lumban Tobing
  2. Pramono Urges MUI to Strengthen Synergy in Maintaining Jakarta’s Harmony

    access_time12-08-2026 remove_red_eye603 personDessy Suciati
  3. 21 Parking Locations Prepared for Indonesian Independence Day Celebrations

    access_time15-08-2026 remove_red_eye454 personAldi Geri Lumban Tobing
  4. Fire Site in Utan Kayu Utara Being Cleared

    access_time11-08-2026 remove_red_eye445 personNurito
  5. Transportation Agency Prepares Traffic Management Plan for Indonesia's 81st Anniversary Celebrations

    access_time15-08-2026 remove_red_eye431 personAldi Geri Lumban Tobing