IPAL Project on di Panggang Island Stagnated

The waste water treatment plants (IPAL) construction on Panggang Island, Seribu Islands, stagnated.

Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent

It will be stopped if the contractor cannot finish it on December 5, 2016.

IPAL Construction on Panggang Island Accelerated

"Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent," expressed Mustajab, Head of Seribu Islands Water Management Sub-dept, Saturday (12/3).

He went on the say that if they cannot met it, his party will stop the contract. 

"If the contract was stopped, they must fix the excavation and restore it as before," he stated. 

As known, the project has spent Rp 3 billion and was targeted to be finished on December 5. Then another project on Tidung Island has spent Rp 10.2 billion.

Currently, its project has reached 75 percent, and is targeted to be finished in the upcoming December.

Linked News
Popular News indeks
  1. Transjabodetabek PIK 2-Blok M Route Serves 1.4 Million Passengers

    access_time24-05-2026 remove_red_eye1874 personAldi Geri Lumban Tobing
  2. North Jakarta KPKP Ensures Sacrificial Meat is Safe for Consumption

    access_time27-05-2026 remove_red_eye851 personAnita Karyati
  3. Jakarta Government Hosts Jakarta Sales Mission in China

    access_time25-05-2026 remove_red_eye741 personAldi Geri Lumban Tobing
  4. Commission E Pushes for Evaluation of Free Private School Program

    access_time25-05-2026 remove_red_eye731 personFakhrizal Fakhri
  5. Dharma Jaya Supports Jakarta PWNU Qurban Program

    access_time27-05-2026 remove_red_eye719 personAldi Geri Lumban Tobing