Kinerja Kontraktor IPAL Pulau Seribu Dievaluasi

IPAL Project on di Panggang Island Stagnated

The waste water treatment plants (IPAL) construction on Panggang Island, Seribu Islands, stagnated.

Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent

It will be stopped if the contractor cannot finish it on December 5, 2016.

IPAL Construction on Panggang Island Accelerated

"Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent," expressed Mustajab, Head of Seribu Islands Water Management Sub-dept, Saturday (12/3).

He went on the say that if they cannot met it, his party will stop the contract. 

"If the contract was stopped, they must fix the excavation and restore it as before," he stated. 

As known, the project has spent Rp 3 billion and was targeted to be finished on December 5. Then another project on Tidung Island has spent Rp 10.2 billion.

Currently, its project has reached 75 percent, and is targeted to be finished in the upcoming December.

Linked News
Popular News indeks
  1. Jakarta Pushed for Education Equity to Retain Top Student City Rank

    access_time19-10-2026 remove_red_eye862 personFakhrizal Fakhri
  2. Transjakarta Modifies Mikrotrans Routes JAK 48A, JAK 50, and JAK 79

    access_time12-10-2026 remove_red_eye548 personAldi Geri Lumban Tobing
  3. Dengue Cases Decline in Jakarta as Prevention Efforts Intensify

    access_time16-10-2026 remove_red_eye523 personAldi Geri Lumban Tobing
  4. CiLung Festival Lets Visitors Ride Boats Made from Recycled Plastic Bottles

    access_time16-10-2026 remove_red_eye512 personAldi Geri Lumban Tobing
  5. An-Nur Floating Mosque Opens After Years of Waiting

    access_time16-10-2026 remove_red_eye499 personFakhrizal Fakhri