Kinerja Kontraktor IPAL Pulau Seribu Dievaluasi

IPAL Project on di Panggang Island Stagnated

The waste water treatment plants (IPAL) construction on Panggang Island, Seribu Islands, stagnated.

Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent

It will be stopped if the contractor cannot finish it on December 5, 2016.

IPAL Construction on Panggang Island Accelerated

"Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent," expressed Mustajab, Head of Seribu Islands Water Management Sub-dept, Saturday (12/3).

He went on the say that if they cannot met it, his party will stop the contract. 

"If the contract was stopped, they must fix the excavation and restore it as before," he stated. 

As known, the project has spent Rp 3 billion and was targeted to be finished on December 5. Then another project on Tidung Island has spent Rp 10.2 billion.

Currently, its project has reached 75 percent, and is targeted to be finished in the upcoming December.

Linked News
Popular News indeks
  1. Closure of Railway Level Crossings Socialized

    access_time13-05-2026 remove_red_eye2410 personTiyo Surya Sakti
  2. Telkomsel Digiland Run 2026 Parking Lot List: Check Now!

    access_time14-05-2026 remove_red_eye1128 personAldi Geri Lumban Tobing
  3. Waste Sorting Movement Boosts Circular Economy

    access_time12-05-2026 remove_red_eye878 personFakhrizal Fakhri
  4. Pramono: Jakarta Remains the Capital City Until a Presidential Decree Is Issued

    access_time13-05-2026 remove_red_eye850 personDessy Suciati
  5. Fire Burns Five Houses in Cengkareng Extinguished

    access_time12-05-2026 remove_red_eye768 personBudhi Firmansyah Surapati