IPAL Project on di Panggang Island Stagnated

The waste water treatment plants (IPAL) construction on Panggang Island, Seribu Islands, stagnated.

Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent

It will be stopped if the contractor cannot finish it on December 5, 2016.

IPAL Construction on Panggang Island Accelerated

"Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent," expressed Mustajab, Head of Seribu Islands Water Management Sub-dept, Saturday (12/3).

He went on the say that if they cannot met it, his party will stop the contract. 

"If the contract was stopped, they must fix the excavation and restore it as before," he stated. 

As known, the project has spent Rp 3 billion and was targeted to be finished on December 5. Then another project on Tidung Island has spent Rp 10.2 billion.

Currently, its project has reached 75 percent, and is targeted to be finished in the upcoming December.

Linked News
Popular News indeks
  1. Pramono Prioritizes Construction of Cakung Regional Hospital

    access_time18-04-2025 remove_red_eye469 personFakhrizal Fakhri
  2. Governor Pramono Joins Cycling in Jakarta Silaturahride 2025

    access_time19-04-2025 remove_red_eye408 personBudhi Firmansyah Surapati
  3. Jakarta to Make Public Transportation Free on April 24, 2025

    access_time18-04-2025 remove_red_eye320 personAldi Geri Lumban Tobing
  4. City Goverment Encourages Residents to Use Public Transportation

    access_time21-04-2025 remove_red_eye284 personFakhrizal Fakhri
  5. Transjakarta Applies Special Fares for Female Customers

    access_time20-04-2025 remove_red_eye266 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik