You don't have javascript enabled. Good luck with that.
Pencarian
Kinerja Kontraktor IPAL Pulau Seribu Dievaluasi

IPAL Project on di Panggang Island Stagnated

The waste water treatment plants (IPAL) construction on Panggang Island, Seribu Islands, stagnated.

Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent

It will be stopped if the contractor cannot finish it on December 5, 2016.

IPAL Construction on Panggang Island Accelerated

"Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent," expressed Mustajab, Head of Seribu Islands Water Management Sub-dept, Saturday (12/3).

He went on the say that if they cannot met it, his party will stop the contract. 

"If the contract was stopped, they must fix the excavation and restore it as before," he stated. 

As known, the project has spent Rp 3 billion and was targeted to be finished on December 5. Then another project on Tidung Island has spent Rp 10.2 billion.

Currently, its project has reached 75 percent, and is targeted to be finished in the upcoming December.

Linked News
Popular News indeks
  1. Pram-Rano Attend Bung Karno Festival at Proklamasi Park

    access_time20-06-2026 remove_red_eye789 personFolmer
  2. Rano Officially Opens Discover Betawi Art and Culture 2026

    access_time19-06-2026 remove_red_eye425 personBudhi Firmansyah Surapati
  3. Metropolitan City Rally 2026 to Be Held at City Hall

    access_time19-06-2026 remove_red_eye392 personAldi Geri Lumban Tobing
  4. South Jakarta Strengthens Efforts to Boost Regional Tax Revenue

    access_time15-06-2026 remove_red_eye379 personTiyo Surya Sakti
  5. Education Agency: Student Admissions to be Objective, Transparent, and Inclusive

    access_time15-06-2026 remove_red_eye370 personAldi Geri Lumban Tobing