Kinerja Kontraktor IPAL Pulau Seribu Dievaluasi

IPAL Project on di Panggang Island Stagnated

The waste water treatment plants (IPAL) construction on Panggang Island, Seribu Islands, stagnated.

Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent

It will be stopped if the contractor cannot finish it on December 5, 2016.

IPAL Construction on Panggang Island Accelerated

"Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent," expressed Mustajab, Head of Seribu Islands Water Management Sub-dept, Saturday (12/3).

He went on the say that if they cannot met it, his party will stop the contract. 

"If the contract was stopped, they must fix the excavation and restore it as before," he stated. 

As known, the project has spent Rp 3 billion and was targeted to be finished on December 5. Then another project on Tidung Island has spent Rp 10.2 billion.

Currently, its project has reached 75 percent, and is targeted to be finished in the upcoming December.

Linked News
Popular News indeks
  1. Jakarta Removes Gibran’s Portraits Across All Government Offices

    access_time16-11-2026 remove_red_eye791 personFakhrizal Fakhri
  2. Transjakarta Offers Free Rides for Jakarta Vertical Run 2026 Participants

    access_time14-11-2026 remove_red_eye616 personAldi Geri Lumban Tobing
  3. Governor Approves Removal of Seven Unauthorized Houses on Dispora Land

    access_time13-11-2026 remove_red_eye586 personFakhrizal Fakhri
  4. Pramono Outlines Measures to Address Five Issues in Kramat Jati

    access_time13-11-2026 remove_red_eye574 personFakhrizal Fakhri
  5. BI and Jakarta Government Deepen Investment, Creative Economy Collaboration

    access_time09-11-2026 remove_red_eye554 personAldi Geri Lumban Tobing