IPAL Project on di Panggang Island Stagnated

The waste water treatment plants (IPAL) construction on Panggang Island, Seribu Islands, stagnated.

Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent

It will be stopped if the contractor cannot finish it on December 5, 2016.

IPAL Construction on Panggang Island Accelerated

"Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent," expressed Mustajab, Head of Seribu Islands Water Management Sub-dept, Saturday (12/3).

He went on the say that if they cannot met it, his party will stop the contract. 

"If the contract was stopped, they must fix the excavation and restore it as before," he stated. 

As known, the project has spent Rp 3 billion and was targeted to be finished on December 5. Then another project on Tidung Island has spent Rp 10.2 billion.

Currently, its project has reached 75 percent, and is targeted to be finished in the upcoming December.

Linked News
Popular News indeks
  1. Transjakarta Adjusts Operations Due to Public Demonstration

    access_time12-06-2026 remove_red_eye1859 personAldi Geri Lumban Tobing
  2. Pramono Launches Jumbo Biopores, Aims for Jakarta Waste Management Blueprint

    access_time07-06-2026 remove_red_eye1027 personDessy Suciati
  3. Pramono: Transjabodetabek Fare Adjustment Based on Careful Consideration

    access_time10-06-2026 remove_red_eye1016 personDessy Suciati
  4. BTN JAKIM 2026, Traffic Engineering and Alternative Routes Provided

    access_time11-06-2026 remove_red_eye854 personAldi Geri Lumban Tobing
  5. Accelerating Jakarta`s Global City Development, Pramono Inaugurates Urban Knowledge Hub

    access_time08-06-2026 remove_red_eye787 personDessy Suciati