IPAL Project on di Panggang Island Stagnated

The waste water treatment plants (IPAL) construction on Panggang Island, Seribu Islands, stagnated.

Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent

It will be stopped if the contractor cannot finish it on December 5, 2016.

IPAL Construction on Panggang Island Accelerated

"Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent," expressed Mustajab, Head of Seribu Islands Water Management Sub-dept, Saturday (12/3).

He went on the say that if they cannot met it, his party will stop the contract. 

"If the contract was stopped, they must fix the excavation and restore it as before," he stated. 

As known, the project has spent Rp 3 billion and was targeted to be finished on December 5. Then another project on Tidung Island has spent Rp 10.2 billion.

Currently, its project has reached 75 percent, and is targeted to be finished in the upcoming December.

Linked News
Popular News indeks
  1. Indonesia-Singapore Match: 80 Dishub Personnel Deployed to Manage Traffic Around GBK

    access_time25-09-2026 remove_red_eye1084 personAldi Geri Lumban Tobing
  2. Jakarta International Stadium Sets Up Transit Schemes for The Weeknd Concert

    access_time24-09-2026 remove_red_eye743 personAldi Geri Lumban Tobing
  3. Pramono: Climate Action Must Deliver Tangible Benefits to Residents

    access_time25-09-2026 remove_red_eye516 personDessy Suciati
  4. Pasar Baru Rowing Race Set to Take Place This Sunday

    access_time25-09-2026 remove_red_eye476 personFolmer
  5. Kelapa Gading-Manggarai LRT Serves 100,343 Passengers

    access_time26-09-2026 remove_red_eye455 personAldi Geri Lumban Tobing