photo Suparni - Beritajakarta.id

IPAL Project on di Panggang Island Stagnated

The waste water treatment plants (IPAL) construction on Panggang Island, Seribu Islands, stagnated.

Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent

It will be stopped if the contractor cannot finish it on December 5, 2016.

IPAL Construction on Panggang Island Accelerated

"Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent," expressed Mustajab, Head of Seribu Islands Water Management Sub-dept, Saturday (12/3).

He went on the say that if they cannot met it, his party will stop the contract. 

"If the contract was stopped, they must fix the excavation and restore it as before," he stated. 

As known, the project has spent Rp 3 billion and was targeted to be finished on December 5. Then another project on Tidung Island has spent Rp 10.2 billion.

Currently, its project has reached 75 percent, and is targeted to be finished in the upcoming December.

Linked News
Popular News indeks
  1. Rano: Pancasila is the Big House for Indonesia's Diversity

    access_time02-06-2025 remove_red_eye522 personBudhi Firmansyah Surapati
  2. Rano Requests PBSI to Hold Governor's Cup Championship

    access_time31-05-2025 remove_red_eye412 personBudhi Firmansyah Surapati
  3. Transjabodetabek Bogor–Blok M Route and Corridor 13 Extension Begin Operations

    access_time05-06-2025 remove_red_eye356 personDessy Suciati
  4. Friendly Countries' Ambassadors Participate in Famtrip to Seribu Islands

    access_time05-06-2025 remove_red_eye301 personAldi Geri Lumban Tobing
  5. No Odd-Even Restrictions in Jakarta on June 6-9, 2025

    access_time03-06-2025 remove_red_eye268 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik