Kinerja Kontraktor IPAL Pulau Seribu Dievaluasi

IPAL Project on di Panggang Island Stagnated

The waste water treatment plants (IPAL) construction on Panggang Island, Seribu Islands, stagnated.

Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent

It will be stopped if the contractor cannot finish it on December 5, 2016.

IPAL Construction on Panggang Island Accelerated

"Until now, IPAL construction has reached 47 percent. Based on the target, it should be 83 percent," expressed Mustajab, Head of Seribu Islands Water Management Sub-dept, Saturday (12/3).

He went on the say that if they cannot met it, his party will stop the contract. 

"If the contract was stopped, they must fix the excavation and restore it as before," he stated. 

As known, the project has spent Rp 3 billion and was targeted to be finished on December 5. Then another project on Tidung Island has spent Rp 10.2 billion.

Currently, its project has reached 75 percent, and is targeted to be finished in the upcoming December.

Linked News
Popular News indeks
  1. Jakarta Set to Launch Historic Municipal Bonds, Pramono Says

    access_time01-07-2026 remove_red_eye1142 personDessy Suciati
  2. Jakarta Government Quickly Addresses Toddler Falling into a Hole Incident

    access_time29-06-2026 remove_red_eye662 personDessy Suciati
  3. Central Jakarta Offers Free Tattoo Removal Service to 100 Residents

    access_time29-06-2026 remove_red_eye521 personFolmer
  4. Asylum Seekers Urged Not to Occupy Public Facilities Outside UNHCR Office

    access_time02-07-2026 remove_red_eye502 personTiyo Surya Sakti
  5. Jakarta Prepares 11 New Housing Projects for Better Living

    access_time30-06-2026 remove_red_eye482 personFakhrizal Fakhri