 Pembangunan JLNT Tendean-Ciledug Sudah 99,99 Persen

Tendean-Ciledug JLNT Targeted to Complete This Month

The Tendean-Ciledug Non-Toll Flyover (JLNT) project, especially for Transjakarta bus plying corridor XIII is almost done or has touched 99.99 percent.

We're targeting to finish it this month

Jakarta Bina Marga Dept. Head, Yusmada Faizal disclosed the project is only leaving asphalting process in Ciledug. The volume is small or less than 100 meters.

"It has entered finishing stage. We're targeting to finish it this month," he expressed, Saturday (2/11).

300 LED Lamps to Be Installed at Tendean-Ciledug JLNT

For the bottom part, he added, has entered finishing stage. As planned, regular road will also be concreted for durability.

"We'll test it in April-May. Hopefully, the bus can already operate in the upcoming June," he closed.

Linked News
Popular News indeks
  1. Pramono Pushes to Complete Long-Delayed Pluit JLNT by March 2027

    access_time20-11-2026 remove_red_eye701 personDessy Suciati
  2. JAF 2026 Highlights Maritime Heritage and Coastal Architecture

    access_time21-11-2026 remove_red_eye691 personAnita Karyati
  3. Hosted in Sydney, Pramono Discusses Opening Australian Campuses in Jakarta

    access_time25-11-2026 remove_red_eye682 personDessy Suciati
  4. Jakarta Strengthens ASEAN Cooperation on Climate, Transport, and Youth

    access_time20-11-2026 remove_red_eye640 personFolmer
  5. BORJU Markets 200 Local Products

    access_time20-11-2026 remove_red_eye609 personAnita Karyati