First Phase of MRT Project Targeted to Finish March 2019

First phase (Lebak Bulus-Bundaran HI) of Mass Rapid Transit (MRT) project construction keeps accelerating. This mass transportation project is targeted to be finished on March 2019.

Recent MRT first phase progress is reached 66 percent. Until the end of this year we targeted to reach 93 percent

"Train have been produced. First train will arrive on next year's April," said William Sabandar, President Director of PT. MRT at City Council Building, Tuesday (3/7).

He expressed the first phase of MRT project cost is Rp 15 trillion. 13 MRT stations to be provided from Lebak Bulus to Bundaran HI with distance of 30 minutes.

2019, MRT Second Phase Construction Started

"Before 2018 Asian Games, all constructions of MRT first phase is targeted to be finished," he said.

He added that his side also in the middle of accelerating MRT construction project for second phase (Bundaran HI-Ancol) along 14.6 kilometers that targeted will start to build in the beginning of next year.

"Recent MRT first phase progress has reached 66 percent. Until the end of this year we targeted to reach 93 percent," he closed.      

Linked News
Popular News indeks
  1. MSMEs Bazaar Held at Binus Anggrek Campus

    access_time30-10-2024 remove_red_eye950 personTP Moan Simanjuntak
  2. 250 High School Students in N. Jakarta Learn to Create Digital Content

    access_time01-11-2024 remove_red_eye653 personBudhi Firmansyah Surapati
  3. Satpol PP Expels Illegal Participants at Sudirman - Thamrin CFD

    access_time27-10-2024 remove_red_eye454 personBudhi Firmansyah Surapati
  4. South Jakarta City Government Accelerates Stop BABS

    access_time31-10-2024 remove_red_eye394 personTiyo Surya Sakti
  5. Traffic Arrangement Applied on Jalan Tambak

    access_time28-10-2024 remove_red_eye370 personAldi Geri Lumban Tobing