Pembangunan Tanggul A NCICD Muara Baru Sudah 55 Persen
.
photo istimewa - Beritajakarta.id

NCICD Embankment A Project Has Reached 55 Percent

The construction of the National Capital Integrated Coastal Development (NCICD) Embankment A in Muara Baru by Public Works and Public Housing Ministry has touched 55 percent.

It will be accelerated and is targeted to be completed in the forthcoming December, from the initial plan in early April 2018

Ferdinanto, Committing Officer for National Higher Education Fund Corporation (PTPIN) said the embankment project is in accordance with Presidential Regulation No. 58/2017 about acceleration of national strategic projects.

"It will be accelerated and is targeted to be completed in the forthcoming December, from the initial plan in early April 2018," he stated, Wednesday (7/26).

Acting Governor to Visit NCICD Phase A Construction

The construction process on the second phase of the first package embankment (Muara Baru-Pluit) as long as 1.2 kilometers is accelerated. Hopefully, it could be completed as expected.

"No delay. The construction has reached 55 percent so far," he closed.

Linked News
Popular News indeks
  1. Commission E Urges Residents to Increase Role in Preventing DHF

    access_time19-12-2024 remove_red_eye1219 personDessy Suciati
  2. Transjakarta Adjusting Service as Simpang Pramuka and Rawamangun Bus Stops Closed

    access_time18-12-2024 remove_red_eye1056 personAldi Geri Lumban Tobing
  3. Transjakarta, Telkomsel to Improve Service for Customers

    access_time19-12-2024 remove_red_eye910 personAldi Geri Lumban Tobing
  4. Acting Governor Monitors Food Stock at Kramat Jati and Cipinang Markets

    access_time19-12-2024 remove_red_eye736 personFolmer
  5. TMII Prepares Stuntman Show to Music Concert

    access_time23-12-2024 remove_red_eye693 personNurito