NCICD Embankment A Project Has Reached 55 Percent

The construction of the National Capital Integrated Coastal Development (NCICD) Embankment A in Muara Baru by Public Works and Public Housing Ministry has touched 55 percent.

It will be accelerated and is targeted to be completed in the forthcoming December, from the initial plan in early April 2018

Ferdinanto, Committing Officer for National Higher Education Fund Corporation (PTPIN) said the embankment project is in accordance with Presidential Regulation No. 58/2017 about acceleration of national strategic projects.

"It will be accelerated and is targeted to be completed in the forthcoming December, from the initial plan in early April 2018," he stated, Wednesday (7/26).

Acting Governor to Visit NCICD Phase A Construction

The construction process on the second phase of the first package embankment (Muara Baru-Pluit) as long as 1.2 kilometers is accelerated. Hopefully, it could be completed as expected.

"No delay. The construction has reached 55 percent so far," he closed.

Linked News
Popular News indeks
  1. BMKG: Sunny to Cloudy Skies Forecast Across Jakarta Today

    access_time11-09-2026 remove_red_eye1707 personDessy Suciati
  2. Jakarta Reallocates Funds for Rp 250M Suckermouth Catfish Study After Pramono’s Direct Order

    access_time10-09-2026 remove_red_eye700 personFakhrizal Fakhri
  3. Pramono Urges Jakmania to Keep Jakarta Safe

    access_time11-09-2026 remove_red_eye458 personDessy Suciati
  4. Pramono Endorses Five-City Tour for Jazz Goes to Campus

    access_time12-09-2026 remove_red_eye440 personDessy Suciati
  5. No Damage Reported Following Magnitude 5.9 Seribu Islands Quake

    access_time12-09-2026 remove_red_eye426 personBudhi Firmansyah Surapati