Pembangunan Tanggul A NCICD Muara Baru Sudah 55 Persen
.
photo istimewa - Beritajakarta.id

NCICD Embankment A Project Has Reached 55 Percent

The construction of the National Capital Integrated Coastal Development (NCICD) Embankment A in Muara Baru by Public Works and Public Housing Ministry has touched 55 percent.

It will be accelerated and is targeted to be completed in the forthcoming December, from the initial plan in early April 2018

Ferdinanto, Committing Officer for National Higher Education Fund Corporation (PTPIN) said the embankment project is in accordance with Presidential Regulation No. 58/2017 about acceleration of national strategic projects.

"It will be accelerated and is targeted to be completed in the forthcoming December, from the initial plan in early April 2018," he stated, Wednesday (7/26).

Acting Governor to Visit NCICD Phase A Construction

The construction process on the second phase of the first package embankment (Muara Baru-Pluit) as long as 1.2 kilometers is accelerated. Hopefully, it could be completed as expected.

"No delay. The construction has reached 55 percent so far," he closed.

Linked News
Popular News indeks
  1. Tanah Abang SDA Taskforce Normalizes Channels in Two Locations

    access_time12-05-2025 remove_red_eye465 personFolmer
  2. Community Work Held to Clean Environment in Petamburan

    access_time11-05-2025 remove_red_eye358 personFolmer
  3. Food Station Signs Farming Contracts in Rorotan

    access_time12-05-2025 remove_red_eye294 personAldi Geri Lumban Tobing
  4. Commission D Supports Construction of Rorotan Rusunawa

    access_time10-05-2025 remove_red_eye260 personFakhrizal Fakhri
  5. Pramono Focuses on Increasing Equal Access to Education

    access_time15-05-2025 remove_red_eye242 personDessy Suciati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik