Pembangunan Tanggul A NCICD Muara Baru Sudah 55 Persen
.
photo istimewa - Beritajakarta.id

NCICD Embankment A Project Has Reached 55 Percent

The construction of the National Capital Integrated Coastal Development (NCICD) Embankment A in Muara Baru by Public Works and Public Housing Ministry has touched 55 percent.

It will be accelerated and is targeted to be completed in the forthcoming December, from the initial plan in early April 2018

Ferdinanto, Committing Officer for National Higher Education Fund Corporation (PTPIN) said the embankment project is in accordance with Presidential Regulation No. 58/2017 about acceleration of national strategic projects.

"It will be accelerated and is targeted to be completed in the forthcoming December, from the initial plan in early April 2018," he stated, Wednesday (7/26).

Acting Governor to Visit NCICD Phase A Construction

The construction process on the second phase of the first package embankment (Muara Baru-Pluit) as long as 1.2 kilometers is accelerated. Hopefully, it could be completed as expected.

"No delay. The construction has reached 55 percent so far," he closed.

Linked News
Popular News indeks
  1. Deputy Gov Rano: Meat Stocks Secured Up to Ramadhan

    access_time22-02-2025 remove_red_eye551 personBudhi Firmansyah Surapati
  2. Jakarta to Hold Cheap Food Bazaar at 193 Locations

    access_time22-02-2025 remove_red_eye445 personBudhi Firmansyah Surapati
  3. Pramono - Rano Expected to Realize Better Resident Welfare

    access_time20-02-2025 remove_red_eye309 personBudhi Firmansyah Surapati
  4. Jakartans Invited to Participate in HPSN 2025 Event

    access_time21-02-2025 remove_red_eye301 personAldi Geri Lumban Tobing
  5. 41 Wild Cats in Cikoko Sterilized

    access_time21-02-2025 remove_red_eye295 personTiyo Surya Sakti