RPTRA Construction in Meruya Selatan is Accelerated
Reported by Folmer | Translated by Maria Inggita
Menara RPTRA construction in Meruya Selatan Urban Village, Kembangan, West Jakarta, is keep accelerated. Dozens of workers are deployed to finish RPTRA construction which is built above land with around 1,500 square meters wide.
We have asked project implementers to accelerate the construction by adding some workers
West Jakarta Economy and Development Assistant, Fredy Setiawan said, Menara RPTRA construction progress has reached 40 percent. Project implementers has been asked to accelerate the construction thus it can be inaugurated in October.
"We have asked project implementers to accelerate the construction by adding some workers. Thus Menara RPTRA can be functioned and inaugurated in early October," he said on Monday (9/11) afternoon.
Regional Heads in W. Jakarta Asked to Monitor RPTRA DevelopmentHe is optimistic Menara RPTRA and other 19 RPTRAs construction in West Jakarta can be inaugurated in early October.
"Based on contract, 20 RPTRAs construction is planned to be finished in December. But at least it can be functioned in early October," he expressed.
He added, after 20 RPTRAs construction has been done, West Jakarta will have 44 RPTRAs.
"Last year, 24 RPTRAs have been built and 20 more have been added which construction is accelerated now," he closed.