Pembangunan 15 RPTRA di Jakpus Sudah 84,06 Persen

Construction of 15 RPTRAs in C. Jakarta Has Reached 84 Percent

The 15 RPTRAs construction that spread in Central Jakarta has touched 84 percent. It is targeted to be finished next week.

We're optimistic it can be complete before October 10, 2017

"We're optimistic it can be complete before October 10, 2017," expressed Edy Suryaman, Head of Central Jakarta Public Housing and Settlement Sub-dept., Thursday (10/15).

To realize it, his side has spent Rp 22,966,941,250. And now it has entered arrangement stage of jogging track and park.

Djarot Inaugurated Jaka Teratai RPTRA in Jatinegara Kaum

"It often rains lately. That's why we have difficulties to finish it," he closed.

Linked News
Popular News indeks
  1. Jalan Kebon Kelapa I Repaved

    access_time07-07-2026 remove_red_eye1013 personNurito
  2. Jakarta KPU Records More Than 8.2 Million Registered Voters

    access_time06-07-2026 remove_red_eye933 personFolmer
  3. Addressing Collapsed Road in Pulo Gadung is a Priority, Pramono Says

    access_time08-07-2026 remove_red_eye672 personDessy Suciati
  4. Pramono Inaugurates Mayapada Hospital to Improve Healthcare Services

    access_time09-07-2026 remove_red_eye665 personDessy Suciati
  5. MRT Phase 2A Northbound Tunnel Excavation Completed

    access_time09-07-2026 remove_red_eye651 personAldi Geri Lumban Tobing