Construction Progress of Waste Treatment Site in Kemayoran Reaches 70 Percent
Reported by Wuri Setyaningsih | Translated by Maria Inggita
Construction of eco-friendly waste treatment site on Jl. Dakota, Kebon Kosong Urban Village, Kemayoran, Central Jakarta has reached 70 percent. Construction is started since 2017.
We just need to wait for roof installation and cutting machine
Central Jakarta Environment Sub-dept. Head, Marsigit said, Kemayoran Complex Management Center (PPKK) gave 300 square meters land at first.
But during its construction, PPKK gave more land and now it becomes 1,014 square meters wide."First budget was Rp 895 million for 300 meters land. But that budget is less due to addition of land. Then we continue its construction this year. We just need to wait for roof installation and cutting machine," he informed, Thursday (1/18).
PD PAL Jaya Processes Stool Waste Through Pulogebang IPLTHe explained, that site will be equipped with waste bank, waste processing, and a place to provide compost fertilizer.
"We are waiting for plastic and leaf cutting machines. Currently, it is used as transit site for garbage trucks and carts that will transport waste to Bantar Gebang," he conveyed.