Velodrome-Kelapa Gading Route LRT Construction Reaches 65.17 Percent

Light Rail Transit (LRT) Velodrome-Kelapa Gading route construction has reached 65.17 percent.

LRT is still able to operate in July and in August as public transportation for Asian Games

Jakarta Propertindo (Jakpro) Director, Satya Heragandhi mentioned, weather condition is one of his problems in construction. Because his side needs to stop the construction work while raining.

LRT Construction Project Reaches 63 Percent

"LRT is still able to operate in July and in August as public transportation for Asian Games," he informed, Monday (3/12).

He added, currently all systems have been connected. Such as system for rail acceleration and system to control telecommunication and signalling have been connected.

"Now we are focus to accelerate the rail work," he affirmed.

Linked News
Popular News indeks
  1. Five Transjabodetabek Routes will Be Added to Tackle Traffic Congestion

    access_time09-05-2025 remove_red_eye670 personDessy Suciati
  2. Tanah Abang SDA Taskforce Normalizes Channels in Two Locations

    access_time12-05-2025 remove_red_eye461 personFolmer
  3. Community Work Held to Clean Environment in Petamburan

    access_time11-05-2025 remove_red_eye355 personFolmer
  4. Baduy Tribe Meets Pramono-Rano, Leaves Message of Protecting Nature

    access_time09-05-2025 remove_red_eye300 personDessy Suciati
  5. Reviewing Mookervart IPA, Pramono Wants to Improve Clean Water Services

    access_time09-05-2025 remove_red_eye292 personDessy Suciati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik