 Pembanguan LRT Rute Veldrome-Kelapa Gading Sudah 65,17 Persen

Velodrome-Kelapa Gading Route LRT Construction Reaches 65.17 Percent

Light Rail Transit (LRT) Velodrome-Kelapa Gading route construction has reached 65.17 percent.

LRT is still able to operate in July and in August as public transportation for Asian Games

Jakarta Propertindo (Jakpro) Director, Satya Heragandhi mentioned, weather condition is one of his problems in construction. Because his side needs to stop the construction work while raining.

LRT Construction Project Reaches 63 Percent

"LRT is still able to operate in July and in August as public transportation for Asian Games," he informed, Monday (3/12).

He added, currently all systems have been connected. Such as system for rail acceleration and system to control telecommunication and signalling have been connected.

"Now we are focus to accelerate the rail work," he affirmed.

Linked News
Popular News indeks
  1. Pramono Affirms Commitment to Enhancing Regional Financial Management Quality

    access_time02-04-2026 remove_red_eye790 personTiyo Surya Sakti
  2. Pramono Calls for Enhanced Synergy at DPRD Post-Eid Gathering

    access_time30-03-2026 remove_red_eye697 personDessy Suciati
  3. Banners Prohibiting Illegal Parking Levies Installed at Blok M Square

    access_time02-04-2026 remove_red_eye636 personTiyo Surya Sakti
  4. Kampung Rambutan Terminal Sees Increase in Intercity Bus Passengers

    access_time03-04-2026 remove_red_eye548 personNurito
  5. Gov Pramono: Jakarta Prepared to Adopt Weekly WFH Scheme

    access_time30-03-2026 remove_red_eye444 personDessy Suciati