Two Months, Sheet Pile Repair at Jalan Jingga Completed
access_time March 26 2018 02:24 PM remove_red_eye 1110
Reported by Budhi Firmansyah Surapati | Translated by Nugroho Adibrata
Reported by Budhi Firmansyah Surapati | Translated by Nugroho Adibrata
The connecting channel's sheet pile (locally known as turap) as long as 161 meters on Jalan Jingga Raya, Kelapa Gading Timur Urban Village, Kelapa Gading, North Jakarta, whose position is tilted and damaged, is still under repair.
It's already prone to fall. That's why we have done repair since two weeks ago
"The sheet pile itself has 2.8 meters length. Repair is targeted to be completed within two months," expressed Rukmana, Executing Unit Head for Kelapa Gading Sub-district Water Resources, Monday (3/26).
Sheet Pile will Be Installed on Kebon Manggis Collapsed RoadRukmana expressed repair is executed by replacing parts of plaster experiencing tilt. The work uses stone material with vertical and horizontal slub.
"It's already prone to fall. That's why we have done repair since two weeks ago," he stated.