 Perbaikan Turap Longsor di Tendean Square Capai 50 Persen
.
photo Erna Martiyanti - Beritajakarta.id

Repair of Collapsed Sheet Pile in Tendean Square Has Reached 50 Percent

South Jakarta Water Resources Sub-dept. is repairing a collapsed sheet pile on the Krukut River, precisely next to Tendean Square. Thus far, its repair has reached 50 percent.

We repair the sheet pile again. It was collapsed by the end of December 2017

South Jakarta Water Resources Sub-dept. Head, Holy Santoso disclosed, sheet pile is repaired up to 23 meters. This sheet pile was collapsed, as it was used as dredging access of Krukut River.

"We repair the sheet pile again. It was collapsed by the end of December 2017," he expressed, Thursday (4/12).

Collapsed Wall Victims in Kwitang Get Logistic Aid

He explained, sheet pile repair has been started since February. Within one and a half months, it is targeted to be finished.

"After it is finished, water will flow smooth and can reduce flood potential," he told.

In the field, his side has sent 25 officers and 1 unit of heavy equipment to speed up the repair.

Linked News
Popular News indeks
  1. District Community Health Centers in East Jakarta Operate for 24 Hours

    access_time05-04-2025 remove_red_eye511 personNurito
  2. Kalideres Bus Terminal Adds 55 Night Transport Units

    access_time05-04-2025 remove_red_eye415 personTiyo Surya Sakti
  3. Jakarta-France Strengthen Cooperation in Various Sectors

    access_time11-04-2025 remove_red_eye323 personDessy Suciati
  4. 24-Hour Park Activation, City Government Finalizes the Plan

    access_time06-04-2025 remove_red_eye296 personBudhi Firmansyah Surapati
  5. Pramono - Rano Prays for Gontor Students to Succeed in Pursuing Knowledge

    access_time08-04-2025 remove_red_eye292 personDessy Suciati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik