Repair of Collapsed Sheet Pile in Tendean Square Has Reached 50 Percent
access_time April 13 2018 03:32 PM remove_red_eye 1628
Reported by Erna Martiyanti | Translated by Nugroho Adibrata
Reported by Erna Martiyanti | Translated by Nugroho Adibrata
South Jakarta Water Resources Sub-dept. is repairing a collapsed sheet pile on the Krukut River, precisely next to Tendean Square. Thus far, its repair has reached 50 percent.
We repair the sheet pile again. It was collapsed by the end of December 2017
South Jakarta Water Resources Sub-dept. Head, Holy Santoso disclosed, sheet pile is repaired up to 23 meters. This sheet pile was collapsed, as it was used as dredging access of Krukut River.
"We repair the sheet pile again. It was collapsed by the end of December 2017," he expressed, Thursday (4/12).
Collapsed Wall Victims in Kwitang Get Logistic AidHe explained, sheet pile repair has been started since February. Within one and a half months, it is targeted to be finished.
"After it is finished, water will flow smooth and can reduce flood potential," he told.
In the field, his side has sent 25 officers and 1 unit of heavy equipment to speed up the repair.