Pengerukan Waduk Makoopsau I Dimulai

Makoopsau I Reservoir Dredging Started

Starting Friday (5/18), East Jakarta Water Resources (SDA) Sub-dept. dredges Makoopsau I Reservoir in Halim Perdana Kusuma, Makasar. Five heavy equipments owned by Jakarta SDA Dept.'s Alkal Unit are used for this dredging.

We will dredge it into 2.5-3 meters depth. Dredging is targeted to complete in around four months

East Jakarta SDA Sub-dept.'s Maintenance Section Head, Yoserizal said, dredging is done by request from TNI AU. It is reported this reservoir with around 10,750 square meters wide is silting.

Channel on Jalan Walter Monginsidi Dredged

"Because this reservoir is silting, TNI AU requests to dredge it. We immediately coordinate with Alkal Unit to send us heavy equipment," he stated, Friday (5/18).

According to him, it has around one meter depth. His side plans to dredge it until 2.5-3 meters depth. There are four amphibian long arm excavators and one standard excavator used to dredge it.

"We will dredge it into 2.5-3 meters depth. Dredging is targeted to complete in around four months," he conveyed.

Linked News
Popular News indeks
  1. Rano: CIEIE 2026 to Catapult Jakarta’s MSMEs onto the International Stage

    access_time25-08-2026 remove_red_eye750 personBudhi Firmansyah Surapati
  2. Jakarta Deploys 120 Personnel to Counteract Traffic Disruption for Today’s Protests

    access_time27-08-2026 remove_red_eye704 personAldi Geri Lumban Tobing
  3. Pramono Pushes for Partnership Between New Toto Tentrem and Tarakan Hospitals

    access_time24-08-2026 remove_red_eye665 personDessy Suciati
  4. Transjakarta Commits to Transport Equality Across the Seribu Islands

    access_time24-08-2026 remove_red_eye529 personAldi Geri Lumban Tobing
  5. Transjakarta Resumes Operations with Strategic Service Adjustments

    access_time28-08-2026 remove_red_eye497 personAldi Geri Lumban Tobing