Jl. Kahfi Water Channel Construction Reaches 90 Percent
Reported by Erna Martiyanti | Translated by Maria Inggita
Current progress of Water channel construction on Jalan Kahfi 1, Jagakarsa, South Jakarta reaches 90 percent.
Currently it has reached 90 percent. Our target is to complete it by the end of this month
This construction is targeted to complete by the end of this month.
South Jakarta Water Resources (SDA) Sub-dept.'s Development Section Head, Didi Sugandhi mentioned, his side will build this 755 meters channels in two sections.
Water Channels in Panggang Island Repaired"Currently it has reached 90 percent. Our target is to complete it by the end of this month," he conveyed, Thursday (7/18).
He expressed to encounter various problems in constructing this channel. Such as to relocate many utility cables. Besides, there is also crossing project that takes a long time to finish.
"After it is built, we hope it can reduce inundation on the location," he added.
He mentioned, his side build water channel on Jalan Kahfi 1 and Jalan Kahfi 2. Segment 1 construction is started from in front of ruko building to the end of Jalan Kahfi 2 then turn into Jalan Kahfi 1 near fish breeding area.
Meanwhile, the second section starts from before police station and formed a crossing that l
eads to Matoa Golf.