 Penataan Trotoar di Pulogebang Capai 45 Persen
.
photo Nurito - Beritajakarta.id

Sidewalk Arrangement in Pulogebang Has Reached 45 Percent

The sidewalk arrangement progress that spends Rp 3.5 billion via APBD towards Jalan Raya Sumarno and Jalan Raya Penggilingan, Pulogebang, Cakung, East Jakarta, as long as 2,483 square meters has reached 45 percent.

It is targeted to be completed by the end of August

East Jakarta Bina Marga Sub-dept. Head, Juaini Yusuf stated, the sidewalk is equipped by 25 ducting boxes for utility network with a distance of about 25 meters. By so, the utility owner has no longer dig the ground on the sidewalk.

Sudirman-Thamrin Sidewalk Arrangement Targeted to Complete Before Asian Games

"It is targeted to be completed by the end of August," he stated, Monday (7/23).

He explained it is done for 24 hours each day. Then for dismantling and cleaning, will be done in the afternoon and casting at night. 

"Jalan Soemarno will have a park by preparing a land whereby its placement will be adapted to the field conditions," he told. 

Linked News
Popular News indeks
  1. Most Residents Satisfied with Pramono-Rano's Performance

    access_time25-06-2025 remove_red_eye314 personDessy Suciati
  2. Pramono Ensures KJP will Continue to Be Distributed

    access_time26-06-2025 remove_red_eye311 personDessy Suciati
  3. No Car Free Day on June 29 to Support Jakarta International Marathon 2025

    access_time24-06-2025 remove_red_eye293 personAldi Geri Lumban Tobing
  4. 19,675 People Visit Ragunan Zoo on Islamic New Year

    access_time27-06-2025 remove_red_eye284 personTiyo Surya Sakti
  5. Here are Parking Spaces around Lapangan Banteng for Jakarta's Anniversary

    access_time21-06-2025 remove_red_eye270 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik