You don't have javascript enabled. Good luck with that.
Pencarian
 Penataan Trotoar di Pulogebang Capai 45 Persen
.
photo Nurito - Beritajakarta.id

Sidewalk Arrangement in Pulogebang Has Reached 45 Percent

The sidewalk arrangement progress that spends Rp 3.5 billion via APBD towards Jalan Raya Sumarno and Jalan Raya Penggilingan, Pulogebang, Cakung, East Jakarta, as long as 2,483 square meters has reached 45 percent.

It is targeted to be completed by the end of August

East Jakarta Bina Marga Sub-dept. Head, Juaini Yusuf stated, the sidewalk is equipped by 25 ducting boxes for utility network with a distance of about 25 meters. By so, the utility owner has no longer dig the ground on the sidewalk.

Sudirman-Thamrin Sidewalk Arrangement Targeted to Complete Before Asian Games

"It is targeted to be completed by the end of August," he stated, Monday (7/23).

He explained it is done for 24 hours each day. Then for dismantling and cleaning, will be done in the afternoon and casting at night. 

"Jalan Soemarno will have a park by preparing a land whereby its placement will be adapted to the field conditions," he told. 

Linked News
Popular News indeks
  1. Rano Inspects Location and Delivers Aid to Fire Victims in Bukit Duri

    access_time20-07-2025 remove_red_eye379 personNurito
  2. Residents Enthusiastically Enjoy the Car Free Day in Kebayoran Lama

    access_time13-07-2025 remove_red_eye359 personTiyo Surya Sakti
  3. Council Urges Free School Programs to Prioritize Principles of Fairness and Quality

    access_time18-07-2025 remove_red_eye330 personFakhrizal Fakhri
  4. Assistance Continues to Be Provided to Bukit Duri Fire Victims

    access_time20-07-2025 remove_red_eye330 personNurito
  5. Traffic Engineering on Jalan Otista to Begin July 20 Due to JPO Revitalization

    access_time17-07-2025 remove_red_eye329 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik