Sidewalk Arrangement in Pulogebang Has Reached 45 Percent
access_time July 23 2018 02:14 PM remove_red_eye 1055
Reported by Nurito | Translated by Nugroho Adibrata
Reported by Nurito | Translated by Nugroho Adibrata
The sidewalk arrangement progress that spends Rp 3.5 billion via APBD towards Jalan Raya Sumarno and Jalan Raya Penggilingan, Pulogebang, Cakung, East Jakarta, as long as 2,483 square meters has reached 45 percent.
It is targeted to be completed by the end of August
East Jakarta Bina Marga Sub-dept. Head, Juaini Yusuf stated, the sidewalk is
equipped by 25 ducting boxes for utility network with a distance of about 25 meters. By so, the utility owner has no longer dig the ground on the sidewalk.Sudirman-Thamrin Sidewalk Arrangement Targeted to Complete Before Asian Games"It is targeted to be completed by the end of August," he stated, Monday (7/23).
He explained it is done for 24 hours each day. Then for dismantling and cleaning, will be done in the afternoon and casting at night.
"Jalan Soemarno will have a park by preparing a land whereby its placement will be adapted to the field conditions," he told.