 Penataan Trotoar di Pulogebang Capai 45 Persen
.
photo Nurito - Beritajakarta.id

Sidewalk Arrangement in Pulogebang Has Reached 45 Percent

The sidewalk arrangement progress that spends Rp 3.5 billion via APBD towards Jalan Raya Sumarno and Jalan Raya Penggilingan, Pulogebang, Cakung, East Jakarta, as long as 2,483 square meters has reached 45 percent.

It is targeted to be completed by the end of August

East Jakarta Bina Marga Sub-dept. Head, Juaini Yusuf stated, the sidewalk is equipped by 25 ducting boxes for utility network with a distance of about 25 meters. By so, the utility owner has no longer dig the ground on the sidewalk.

Sudirman-Thamrin Sidewalk Arrangement Targeted to Complete Before Asian Games

"It is targeted to be completed by the end of August," he stated, Monday (7/23).

He explained it is done for 24 hours each day. Then for dismantling and cleaning, will be done in the afternoon and casting at night. 

"Jalan Soemarno will have a park by preparing a land whereby its placement will be adapted to the field conditions," he told. 

Linked News
Popular News indeks
  1. Environment Agency Supports Efforts to Comply with Vehicle Emissions Test Regulations

    access_time12-03-2025 remove_red_eye500 personAldi Geri Lumban Tobing
  2. Transjakarta Presents Jakarta Symphony Every Saturday Afternoon

    access_time10-03-2025 remove_red_eye421 personAldi Geri Lumban Tobing
  3. North Jakarta PPKD Provides Training for Students with Disabilities

    access_time07-03-2025 remove_red_eye408 personAnita Karyati
  4. Rano Supports Schools to Organize Study Tours to Museums

    access_time08-03-2025 remove_red_eye364 personBudhi Firmansyah Surapati
  5. TMII Launches Jelajah Cerita Ramadan Program with Umroh Grand Prize

    access_time08-03-2025 remove_red_eye363 personNurito

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik