 Penataan Trotoar di Pulogebang Capai 45 Persen

Sidewalk Arrangement in Pulogebang Has Reached 45 Percent

The sidewalk arrangement progress that spends Rp 3.5 billion via APBD towards Jalan Raya Sumarno and Jalan Raya Penggilingan, Pulogebang, Cakung, East Jakarta, as long as 2,483 square meters has reached 45 percent.

It is targeted to be completed by the end of August

East Jakarta Bina Marga Sub-dept. Head, Juaini Yusuf stated, the sidewalk is equipped by 25 ducting boxes for utility network with a distance of about 25 meters. By so, the utility owner has no longer dig the ground on the sidewalk.

Sudirman-Thamrin Sidewalk Arrangement Targeted to Complete Before Asian Games

"It is targeted to be completed by the end of August," he stated, Monday (7/23).

He explained it is done for 24 hours each day. Then for dismantling and cleaning, will be done in the afternoon and casting at night. 

"Jalan Soemarno will have a park by preparing a land whereby its placement will be adapted to the field conditions," he told. 

Linked News
Popular News indeks
  1. Pramono Affirms Commitment to Enhancing Regional Financial Management Quality

    access_time02-04-2026 remove_red_eye795 personTiyo Surya Sakti
  2. Pramono Calls for Enhanced Synergy at DPRD Post-Eid Gathering

    access_time30-03-2026 remove_red_eye704 personDessy Suciati
  3. Banners Prohibiting Illegal Parking Levies Installed at Blok M Square

    access_time02-04-2026 remove_red_eye641 personTiyo Surya Sakti
  4. Kampung Rambutan Terminal Sees Increase in Intercity Bus Passengers

    access_time03-04-2026 remove_red_eye616 personNurito
  5. Gov Pramono: Jakarta Prepared to Adopt Weekly WFH Scheme

    access_time30-03-2026 remove_red_eye448 personDessy Suciati