Pembangunan Skybridge Tanah Abang Capai 25 Persen

Tanah Abang Skybridge Project Has Touched 25 Percent

The development progress Tanah Abang Skybridge or crossing bridge has now reached 25 percent. It is including installation of steel material in zone A and floor installation.

Tanah Abang Skybridge project has touched 25 percent

"Tanah Abang Skybridge project has touched 25 percent," expressed Yoory C Pinontoan, Director Presidential of PD Pembangunan Sarana Jaya, Friday (9/14).

He explained that the development that spent Rp 35.8 billion has entered Zone B with pedestal casting and foundation work, assembly or installation of steel structure buildings and second floor.

Skybridge Project will Be Socialized to Jati Baru PKL

 

The total length of steel material that has been installed is around 187 meters with 12 meters height. For work on the second floor, concrete that has been installed is approximately 115 meters.

He added that the 80 percent of bridge development is carried out at the factory using knock down systems, namely steel frames and structures made separately from the work site.

"Hopefully the bridge that is able to accommodate 446 street vendors can operate on October 15, 2018," he said.

Linked News
Popular News indeks
  1. Jakarta Council Begins Deliberations on New Population and Housing Bylaws

    access_time21-08-2026 remove_red_eye1907 personFakhrizal Fakhri
  2. Pramono Vows to Prioritize Jakarta’s Strategic Development

    access_time22-08-2026 remove_red_eye928 personDessy Suciati
  3. Pramono Commends Madurese Community for Their Vital Role in Building Jakarta

    access_time19-08-2026 remove_red_eye719 personDessy Suciati
  4. Pramono Pushes for Partnership Between New Toto Tentrem and Tarakan Hospitals

    access_time24-08-2026 remove_red_eye612 personDessy Suciati
  5. New LRT Jakarta Route Set for Official Launch on August 26

    access_time22-08-2026 remove_red_eye458 personDessy Suciati