Pembangunan Jembatan Penyeberangan Multiguna Tanah Abang Capai 58 Persen
.
photo Rezki Apriliya Iskandar - Beritajakarta.id

Tanah Abang Skybridge Construction Reaches 58 Percent

Tanah Abang Skybridge construction has reached 58 percent per October 4, 2018.

We are optimistic to finish this project on target

PD. Pembangunan Sarana Jaya, Yoory C. Pinontoan said, skybridge construction which is started on August 3, 2018 is targeted to complete and ready to be used on October 15, 2018.

"Current progress is related to its structure construction, ceiling, precast for 2nd floor, fence on 1st floor, railing on 2nd floor, curb concrete for ramp area, and Block F and Block G connecting bridge," he explained, Thursday (10/4).

Tanah Abang Skybridge Construction Socialized to Jatibaru PKLs

According to him, his side changes construction mechanism by constructing Zone D first and then continues to construct other zones thus the target can be achieved.

"We are optimistic to finish this project on target," he affirmed.

Linked News
Popular News indeks
  1. Jakarta Vice Governor Rano Wishes a Happy Eid al-Fitr 1446 Hijri

    access_time31-03-2025 remove_red_eye589 personFolmer
  2. Monas Prepares to Greet Visitors This Eid Holiday

    access_time30-03-2025 remove_red_eye573 personDessy Suciati
  3. Foul Smell Around JGC Clarified Not Coming from Rorotan RDF

    access_time28-03-2025 remove_red_eye430 personAldi Geri Lumban Tobing
  4. Residents Hope Another Free Homecoming Program Held Next Year

    access_time27-03-2025 remove_red_eye315 personDessy Suciati
  5. Jakarta Ready to Anticipate Potential Tidal Floods

    access_time27-03-2025 remove_red_eye281 personFakhrizal Fakhri

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik