Tanah Abang Skybridge Construction Reaches 58 Percent

Tanah Abang Skybridge construction has reached 58 percent per October 4, 2018.

We are optimistic to finish this project on target

PD. Pembangunan Sarana Jaya, Yoory C. Pinontoan said, skybridge construction which is started on August 3, 2018 is targeted to complete and ready to be used on October 15, 2018.

"Current progress is related to its structure construction, ceiling, precast for 2nd floor, fence on 1st floor, railing on 2nd floor, curb concrete for ramp area, and Block F and Block G connecting bridge," he explained, Thursday (10/4).

Tanah Abang Skybridge Construction Socialized to Jatibaru PKLs

According to him, his side changes construction mechanism by constructing Zone D first and then continues to construct other zones thus the target can be achieved.

"We are optimistic to finish this project on target," he affirmed.

Linked News
Popular News indeks
  1. Most Residents Satisfied with Pramono-Rano's Performance

    access_time25-06-2025 remove_red_eye316 personDessy Suciati
  2. Pramono Ensures KJP will Continue to Be Distributed

    access_time26-06-2025 remove_red_eye314 personDessy Suciati
  3. 19,675 People Visit Ragunan Zoo on Islamic New Year

    access_time27-06-2025 remove_red_eye314 personTiyo Surya Sakti
  4. UK Royal Marine Band Enlivens Jakarta Anniversary

    access_time27-06-2025 remove_red_eye310 personDessy Suciati
  5. No Car Free Day on June 29 to Support Jakarta International Marathon 2025

    access_time24-06-2025 remove_red_eye307 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik