Pembangunan Jembatan Penyeberangan Multiguna Tanah Abang Capai 58 Persen
.
photo Rezki Apriliya Iskandar - Beritajakarta.id

Tanah Abang Skybridge Construction Reaches 58 Percent

Tanah Abang Skybridge construction has reached 58 percent per October 4, 2018.

We are optimistic to finish this project on target

PD. Pembangunan Sarana Jaya, Yoory C. Pinontoan said, skybridge construction which is started on August 3, 2018 is targeted to complete and ready to be used on October 15, 2018.

"Current progress is related to its structure construction, ceiling, precast for 2nd floor, fence on 1st floor, railing on 2nd floor, curb concrete for ramp area, and Block F and Block G connecting bridge," he explained, Thursday (10/4).

Tanah Abang Skybridge Construction Socialized to Jatibaru PKLs

According to him, his side changes construction mechanism by constructing Zone D first and then continues to construct other zones thus the target can be achieved.

"We are optimistic to finish this project on target," he affirmed.

Linked News
Popular News indeks
  1. Pramono Prioritizes Construction of Cakung Regional Hospital

    access_time18-04-2025 remove_red_eye471 personFakhrizal Fakhri
  2. Governor Pramono Joins Cycling in Jakarta Silaturahride 2025

    access_time19-04-2025 remove_red_eye412 personBudhi Firmansyah Surapati
  3. Jakarta to Make Public Transportation Free on April 24, 2025

    access_time18-04-2025 remove_red_eye325 personAldi Geri Lumban Tobing
  4. City Goverment Encourages Residents to Use Public Transportation

    access_time21-04-2025 remove_red_eye285 personFakhrizal Fakhri
  5. Transjakarta Applies Special Fares for Female Customers

    access_time20-04-2025 remove_red_eye274 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik