Pembangunan Jembatan Penyeberangan Multiguna Tanah Abang Capai 58 Persen

Tanah Abang Skybridge Construction Reaches 58 Percent

Tanah Abang Skybridge construction has reached 58 percent per October 4, 2018.

We are optimistic to finish this project on target

PD. Pembangunan Sarana Jaya, Yoory C. Pinontoan said, skybridge construction which is started on August 3, 2018 is targeted to complete and ready to be used on October 15, 2018.

"Current progress is related to its structure construction, ceiling, precast for 2nd floor, fence on 1st floor, railing on 2nd floor, curb concrete for ramp area, and Block F and Block G connecting bridge," he explained, Thursday (10/4).

Tanah Abang Skybridge Construction Socialized to Jatibaru PKLs

According to him, his side changes construction mechanism by constructing Zone D first and then continues to construct other zones thus the target can be achieved.

"We are optimistic to finish this project on target," he affirmed.

Linked News
Popular News indeks
  1. Jakarta to Hold Citywide Lights-Out Initiative

    access_time24-04-2026 remove_red_eye802 personAldi Geri Lumban Tobing
  2. Jakarta Residents Welcome Rp1 Public Transport Fare

    access_time24-04-2026 remove_red_eye618 personNurito
  3. Limiting Gadget Use in Schools Expected to Boost Interaction and Reading Habits

    access_time24-04-2026 remove_red_eye596 personFakhrizal Fakhri
  4. Rano Leads Parking Arrangement on Jalan R.A. Kartini, Lebak Bulus

    access_time24-04-2026 remove_red_eye573 personBudhi Firmansyah Surapati
  5. PT JIEP Targets Shenzhen Businesses with Investment Offers

    access_time24-04-2026 remove_red_eye566 personAldi Geri Lumban Tobing