Malfunctioned Sheetpile on Jalan Kebayoran Lama Repaired
access_time November 13 2018 03:53 PM remove_red_eye 1334
Reported by Wuri Setyaningsih | Translated by Nugroho Adibrata
Reported by Wuri Setyaningsih | Translated by Nugroho Adibrata
Four PPSU personnel under Cipulir Urban Village is repairing a water channel's sheet pile on Jalan Kebayoran Lama, RT 03/02.
The length of the channel is about 2 meters with 40 centimeters width
Cipulir Urban Village Head, Adi Krisno Prayogo stated, prior to repair, the sheet pile was cleaned from mud and trash.
"The length of the channel is about 2 meters with 40 centimeters width," he expressed, Tuesday (11/13).
December, Sheetpile Installation in KBR River CompletedIt is done by using cement, sand, and brick making to further strengthen the sheet pile. It is carried out in the next two to three days.
"Hopefully it can accommodate water in large quantities, as well as can minimize puddles and floods," he hoped.