Landslide Repair in Pademangan Accelerated

Jakarta Water Resouces Dept. continues to speed up work on landslide repairs in Ciliwung River, RT 01/RW 08, Ancol Urban Village, Pademangan, North Jakarta.

Every day we're deploying 40 officers. It's targeted to be completed by the end of December

Until now, part of which is fixed up to 77 meters, or about 60.6 percent of the total length of 127 meters that were damaged.

Governor Monitors Landslide Location in Kalisari

Jakarta Water Resources Dept.'s River and Coast Flow Systems Section, Robert Rajagukguk stated that his side divided the work into two segments. The first stage of the construction up to 77 meter long is now completed already.

"Currently the second phase of the repair is up to 50 meters length," he expressed, Wednesday (11/28).

He added that the Ciliwung River has five meters height. The work itself has been ongoing since October 21, 2018.

"Every day we're deploying 40 officers. It's targeted to be completed by the end of December," he stated.

Linked News
Popular News indeks
  1. Jakarta Government Guarantees Full Medical Care for Bantargebang Landslide Victims

    access_time09-03-2026 remove_red_eye1297 personDessy Suciati
  2. Commission E Supports Restricting Children's Access to Social Media

    access_time09-03-2026 remove_red_eye1128 personFakhrizal Fakhri
  3. Affordable and High-Quality Staple Goods Offered at Ramadan Bazaar

    access_time09-03-2026 remove_red_eye839 personAldi Geri Lumban Tobing
  4. Jakarta Planetarium Rolls Out Varied Shows for Eid al-Fitr Holiday

    access_time11-03-2026 remove_red_eye292 personAldi Geri Lumban Tobing
  5. Jakarta Speeds Up Flood Mitigation Efforts

    access_time08-03-2026 remove_red_eye288 personAldi Geri Lumban Tobing