 Proses Perbaikan Turap Ambrol di Ancol Capai 60 Persen
.
photo Budhi Firmansyah Surapati - Beritajakarta.id

Landslide Repair in Pademangan Accelerated

Jakarta Water Resouces Dept. continues to speed up work on landslide repairs in Ciliwung River, RT 01/RW 08, Ancol Urban Village, Pademangan, North Jakarta.

Every day we're deploying 40 officers. It's targeted to be completed by the end of December

Until now, part of which is fixed up to 77 meters, or about 60.6 percent of the total length of 127 meters that were damaged.

Governor Monitors Landslide Location in Kalisari

Jakarta Water Resources Dept.'s River and Coast Flow Systems Section, Robert Rajagukguk stated that his side divided the work into two segments. The first stage of the construction up to 77 meter long is now completed already.

"Currently the second phase of the repair is up to 50 meters length," he expressed, Wednesday (11/28).

He added that the Ciliwung River has five meters height. The work itself has been ongoing since October 21, 2018.

"Every day we're deploying 40 officers. It's targeted to be completed by the end of December," he stated.

Linked News
Popular News indeks
  1. District Community Health Centers in East Jakarta Operate for 24 Hours

    access_time05-04-2025 remove_red_eye500 personNurito
  2. Backflow at Kampung Rambutan Terminal Increases as Mudik Return Flow Peaks

    access_time04-04-2025 remove_red_eye490 personNurito
  3. Kalideres Bus Terminal Adds 55 Night Transport Units

    access_time05-04-2025 remove_red_eye396 personTiyo Surya Sakti
  4. S. Jakarta Transportation Sub-agency Optimizes Services at Tourist Spots

    access_time03-04-2025 remove_red_eye358 personTiyo Surya Sakti
  5. Ship Surveillance in Bokor Island Waters Intensified for Eid Holiday

    access_time03-04-2025 remove_red_eye313 personAnita Karyati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik